O-RING,EPDM,286MM ID,2.5MM CS
Material 4100019638 · O-RING · Plant 1000
AReorderNormalBelow reorder point
- Material
- 4100019638
- Category
- O-RING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 4 FuncLocs A/B)
- Supplier
- GEMILANG SUPLINDO SENTOSA PT
- Lead time
- 31 d · P80 40 d
- Unit price
- Rp 39,684
Recommendation
- 1.Forecast 11 EA/year: 8.5 unplanned (credibility blend: own history + installed-base prior) + 2.9 from the maintenance plan.
- 2.Lead time ~31 days; expected demand during lead time 0.7.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 20.
- 4.On hand 1 + on order 0 is at or below the reorder point: order 19 now.
- 5.Installed on 4 FuncLoc(s), 1 of them criticality A/B.
- 6.ML early warning: 33% probability of demand in the next 90 days.
Proposed purchase requisition
19 EA
Rp 753,996 · order by 01 Oct 2026
Expected arrival ≈ 31 days
ML early warningSingle source
On hand / on order
1 / 0
no open PO
Today Min / Max
2 / 5
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 8
Rec. Max
20
order qty 12
Service level
100.0%
stockout risk now 24%
Unit price
Rp 39,684
PO history
ML early warning: 33% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 77 days ago, 5 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (6 units) excluded from the baseline.
Demand pattern Lumpy · 5 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 975.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.
Installed on 4 functional locations
1 with criticality A/B · 7 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-419A TURBINE FOR KC-419A | A | 1 | 6 | 2.81 |
| PX_PP-536 HYDROGEN PUMP | C | 4 | 0 | 0.19 |
| PX_KT-383A TURBINE FOR KC-383A | S | 1 | 7 | 3.67 |
| PX_KT-624A TURBINE FOR KC-624A | S | 1 | 3 | 2.39 |
Lead time and procurement
Lead time 31 ± 13 days (PO history, 4 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 03 May 2026 | PR06 Regular replenishment | 7 | Rp 38,392 | 17 Jun 2026 | 45 d |
| 21 Feb 2026 | PR03 Regular replenishment | 7 | Rp 39,883 | 30 Mar 2026 | 37 d |
| 01 Feb 2026 | PR03 Regular replenishment | 2 | Rp 39,485 | 01 Mar 2026 | 28 d |
| 09 Nov 2025 | PR06 Regular replenishment | 8 | Rp 40,512 | 30 Nov 2025 | 21 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 02 Aug 2027 | PX_PP-536 | Pump overhaul | 2.86 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 15 Jul 2026 | Medium | PX_KT-624A | [MSI-B-26-RXR-331/M] Replace line |
| 24 May 2026 | High | PX_KT-383A | KT-383A steam leak at gland |
| 03 Apr 2026 | Medium | PX_KT-419A | KT-419A steam leak at gland |
| 17 Mar 2026 | Medium | PX_KT-419A | Install cover plate for MCP cracking |
| 07 Feb 2026 | Medium | PX_KT-624A | Replace lamp as per PM finding |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 24 Jul 2026 | 4 | 203000004330 | Turnaround |
| 16 Jul 2026 | 2 | 201000025691 | Corrective |
| 12 Jan 2026 | 5 | 201000016153 | Corrective |
| 11 Jan 2026 | 3 | 201000031194 | Corrective |
| 29 Aug 2025 | 2 | 201000002071 | Corrective |
| 27 Jun 2025 | 2 | 203000034428 | Turnaround |
| 30 May 2025 | 1 | 201000012935 | Corrective |