O-RING,EPDM,216MM ID,2.5MM CS

Material 4100019772 · O-RING · Plant 1000

AReduceSlow-moving
Material
4100019772
Category
O-RING
Base unit
EA
MRP type
Stock Item
Criticality
A (6 of 6 FuncLocs A/B)
Supplier
BUANA INSTRUMEN NUSANTARA PT
Lead time
25 d · P80 24 d
Unit price
Rp 20,581

Recommendation

  • 1.Forecast 6.8 EA/year: 6.8 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~25 days; expected demand during lead time 0.5.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 14.
  • 4.Stock 126 exceeds the level to keep (14) by 112.
  • 5.Installed on 6 FuncLoc(s), 6 of them criticality A/B.
  • 6.ML early warning: 68% probability of demand in the next 90 days.
ML early warningLast turnaround used 14Single source
On hand / on order
126 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 7
Rec. Max
14
order qty 7
Service level
100.0%
stockout risk now 0%
Unit price
Rp 20,581
PO history
ML early warning: 68% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 231 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (14 units) excluded from the baseline.

Demand pattern Intermittent · 6 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 938.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 6 functional locations

6 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-247A
SLOP OIL FAN
A294.00
PX_KC-588
CAUSTIC FAN
A121.00
PX_KT-460B
TURBINE FOR KC-460B
A121.96
PX_KC-397A
DILUTION STEAM FAN
A110.57
PX_KC-250D
PROPYLENE FAN
A100.57
PX_PP-1872B
SPENT CAUSTIC PUMP
B100.19

Lead time and procurement

Lead time 25 ± 10 days (PO history, 4 PO lines) · on-time 17%

PR dateTypeQtyUnit priceDeliveryLead time
28 Jun 2026PR05
Project / turnaround
7Rp 20,13125 Jul 202627 d
11 May 2026PR03
Regular replenishment
9Rp 20,88502 Jun 202622 d
16 Dec 2025PR03
Regular replenishment
8Rp 20,27704 Jan 202619 d
27 May 2025PR06
Regular replenishment
12Rp 21,50114 Jun 202518 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
27 Aug 2026HighPX_KC-247AInspect coupling KC-247A
14 Jul 2026MediumPX_KC-247AReplace lamp as per PM finding
29 Jun 2026LowPX_KC-247AKC-247A high vibration
04 Jun 2026LowPX_KC-247AKC-247A bearing temp high
06 Apr 2026MediumPX_KC-247AKC-247A bearing temp high
22 Feb 2026MediumPX_KC-588KC-588 lube oil filter DP high
12 Dec 2025LowPX_KT-460BKT-460B governor valve hunting
20 Nov 2025MediumPX_KC-247AReplace lamp as per PM finding
22 Aug 2025LowPX_KC-247AOverhaul
09 Aug 2025HighPX_KC-247AInspect coupling KC-247A

Recent goods issues

Posting dateQtyOrderOrder type
12 Feb 20263201000032040Corrective
05 Feb 20262204000036606Preventive
23 Dec 20258203000033807Turnaround
20 Dec 20252203000033807Turnaround
12 Dec 20253201000010004Corrective
11 Dec 20252201000019124Corrective
21 Nov 20254203000011208Turnaround
28 Jul 20251201000029079Corrective
22 Jul 20252201000039637Corrective