O-RING,NBR,270MM ID,3.5MM CS

Material 4100019799 · O-RING · Plant 1000

ASafety-criticalReduceExcess
Material
4100019799
Category
O-RING
Base unit
EA
MRP type
Stock Item
Criticality
A (4 of 6 FuncLocs A/B, 3 safety/shutdown valve)
Supplier
ANUGRAH INSTRUMEN SENTOSA PT
Lead time
45 d · P80 73 d
Unit price
Rp 325,204

Recommendation

  • 1.Safety-critical element: installed on 3 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 7.8 EA/year: 7.8 unplanned (recency-weighted compound poisson (own history)).
  • 3.Lead time ~45 days; expected demand during lead time 1.0.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 9, order up to 17.
  • 5.Stock 33 exceeds the level to keep (17) by 16.
  • 6.Installed on 6 FuncLoc(s), 4 of them criticality A/B.
  • 7.ML early warning: 62% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningSingle sourceAbnormal consumption
On hand / on order
33 / 0
no open PO
Today Min / Max
15 / 24
static parameters in BoM
Rec. Min (reorder point)
9
safety stock 9
Rec. Max
17
order qty 8
Service level
100.0%
stockout risk now 0%
Unit price
Rp 325,204
PO history
ML early warning: 62% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 250 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (4 units) excluded from the baseline.

Demand pattern Lumpy · 6 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 811.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 6 functional locations

4 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KC-801
DEMIN WATER FAN
A121.43
PX_PP-336A
RICH AMINE PUMP
A121.05
PX_SDV-742A
METHANOL ISOLATION
B100.06
PX_SDV-1359A
PP-1337 SHUTDOWN VALVE
S110.06
PX_SDV-749
VD-756B SHUTDOWN VALVE
S100.06

Lead time and procurement

Lead time 45 ± 18 days (PO history, 5 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
28 Apr 2026PR03
Regular replenishment
7Rp 325,20414 Jul 202677 d
15 Apr 2026PR06
Regular replenishment
19Rp 330,43429 May 202644 d
09 Feb 2026PR03
Regular replenishment
8Rp 314,97020 Mar 202639 d
24 Jan 2026PR03
Regular replenishment
11Rp 309,89406 Apr 202672 d
02 Sept 2025PR03
Regular replenishment
22Rp 333,75716 Oct 202544 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
12 Apr 2026EmergencyPX_KC-801KC-801 high vibration
03 Apr 2026MediumPX_KT-419AKT-419A steam leak at gland
17 Mar 2026MediumPX_KT-419AInstall cover plate for MCP cracking
05 Dec 2025LowPX_PP-336AOil leak at PP-336A bearing housing
20 Nov 2025MediumPX_KT-419ALeak from packing
10 Nov 2025MediumPX_KT-419APainting KT-419A
03 Sept 2025MediumPX_KT-419AFollow up after steam upset KT-419A
11 Aug 2025MediumPX_PP-336AReplace bearing PP-336A
12 Jul 2025LowPX_KC-801KC-801 bearing temp high
15 May 2025LowPX_KT-419APSM25/Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
30 Apr 20264203000015144Turnaround
24 Jan 20264201000025164Corrective
08 Jan 20261201000030970Corrective
29 Dec 20253201000002026Corrective
04 Dec 20251201000018271Corrective
21 Jul 202532209000036039Other maintenance
25 May 20251201000031996Corrective