O-RING,VITON,224MM ID,5.3MM CS

Material 4100019905 · O-RING · Plant 1000

ASafety-criticalReorderNormalBelow reorder point
Material
4100019905
Category
O-RING
Base unit
EA
MRP type
Stock Item
Criticality
A (5 of 8 FuncLocs A/B, 3 safety/shutdown valve)
Supplier
GEMILANG SUPLINDO SENTOSA PT
Lead time
36 d · P80 56 d
Unit price
Rp 22,757

Recommendation

  • 1.Safety-critical element: installed on 3 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 9.7 EA/year: 9.7 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~36 days; expected demand during lead time 1.0.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 12, order up to 22.
  • 5.On hand 4 + on order 0 is at or below the reorder point: order 18 now.
  • 6.Installed on 8 FuncLoc(s), 5 of them criticality A/B.
  • 7.ML early warning: 61% probability of demand in the next 90 days.
Proposed purchase requisition
18 EA
Rp 409,626 · order by 01 Oct 2026
Expected arrival ≈ 36 days
Safety-critical (SCE)ML early warningSingle source
On hand / on order
4 / 0
no open PO
Today Min / Max
3 / 7
static parameters in BoM
Rec. Min (reorder point)
12
safety stock 12
Rec. Max
22
order qty 10
Service level
100.0%
stockout risk now 3%
Unit price
Rp 22,757
PO history
ML early warning: 61% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 134 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 779.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 8 functional locations

5 with criticality A/B · 8 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_SDV-335A
ON-OFF VALVE
A100.06
PX_SDV-691A
ON-OFF VALVE
A100.06
PX_PP-785A
DILUTION STEAM PUMP
B151.90
PX_SDV-1437
ON-OFF VALVE
B100.06
PX_PP-820A
METHANE PUMP
S120.62
PX_KC-216B
LEAN AMINE FAN
S110.57
PX_PP-1906B
LUBE OIL PUMP
S100.19

Lead time and procurement

Lead time 36 ± 22 days (PO history, 3 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
02 Mar 2026PR06
Regular replenishment
4Rp 22,75731 Mar 202629 d
30 Aug 2025PR03
Regular replenishment
4Rp 22,27827 Sept 202528 d
19 May 2025PR04
Regular (other)
2Rp 23,08701 Aug 202574 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
03 Sept 2026LowPX_PP-820A[MSI-B-26-WPE-117] Permanent repair
25 Jul 2026MediumPX_PP-785A[MSI-B-26-DPX-213/M] Replace line
18 Jun 2026EmergencyPX_PP-785APP-785A abnormal noise
03 Apr 2026MediumPX_KT-419AKT-419A steam leak at gland
17 Mar 2026MediumPX_KT-419AInstall cover plate for MCP cracking
12 Jan 2026MediumPX_PP-785APP-785A discharge pressure low
20 Nov 2025MediumPX_KT-419ALeak from packing
10 Nov 2025MediumPX_KT-419APainting KT-419A
03 Sept 2025MediumPX_KT-419AFollow up after steam upset KT-419A
03 Aug 2025HighPX_PP-785A[MSI-B-25-ZHN-181] Permanent repair

Recent goods issues

Posting dateQtyOrderOrder type
20 May 20263201000006755Corrective
22 Jan 20265201000002546Corrective
07 Dec 20255201000002161Corrective
30 Oct 20252201000007876Corrective