O-RING,EPDM,83MM ID,2.5MM CS
Material 4100020013 · O-RING · Plant 1000
SReorderHighStockout
- Material
- 4100020013
- Category
- O-RING
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- S (0 of 2 FuncLocs A/B)
- Supplier
- LANGIT ELEKTRIK ABADI PT
- Lead time
- 26 d · P80 28 d
- Unit price
- Rp 220,572
Recommendation
- 1.Forecast 2.2 EA/year: 2.2 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~26 days; expected demand during lead time 0.2.
- 3.A 90.2% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 3.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 3 now.
Proposed purchase requisition
3 EA
Rp 661,716 · order by 01 Oct 2026
Expected arrival ≈ 26 days
Convert to Stock ItemLast turnaround used 6Single source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
3
order qty 3
Service level
90.2%
stockout risk now 10%
Unit price
Rp 220,572
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 208 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (8 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~14 days.
Installed on 2 functional locations
0 with criticality A/B · 2 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-422A C4 PRODUCT BLOWER | S | 1 | 6 | 2.71 |
| PX_KT-778A TURBINE FOR KC-778A | S | 1 | 0 | 1.10 |
Lead time and procurement
Lead time 26 ± 13 days (PO history, 3 PO lines) · on-time 46%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 27 Oct 2025 | PR06 Regular replenishment | 6 | Rp 222,495 | 17 Nov 2025 | 21 d |
| 08 Sept 2025 | PR06 Regular replenishment | 6 | Rp 211,561 | 10 Oct 2025 | 32 d |
| 08 Sept 2025 | PR03 Regular replenishment | 3 | Rp 220,572 | 23 Sept 2025 | 15 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 08 Jul 2026 | Medium | PX_KC-422A | KC-422A high vibration |
| 03 Mar 2026 | Low | PX_KC-422A | Leak from packing |
| 20 Jan 2026 | Low | PX_KC-422A | Leak from packing |
| 24 Nov 2025 | Low | PX_KC-422A | KC-422A lube oil filter DP high |
| 19 Oct 2025 | Medium | PX_KC-422A | KC-422A high vibration |
| 23 May 2025 | Low | PX_KC-422A | Overhaul |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 07 Mar 2026 | 2 | 201000018207 | Corrective |
| 06 Jan 2026 | 1 | 201000023699 | Corrective |
| 30 Nov 2025 | 6 | 203000014368 | Turnaround |
| 27 Aug 2025 | 2 | 203000006603 | Turnaround |