O-RING,NBR,123MM ID,5.3MM CS

Material 4100020384 · O-RING · Plant 1000

BReorderNormalBelow reorder point
Material
4100020384
Category
O-RING
Base unit
EA
MRP type
Stock Item
Criticality
B (1 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
29 d · P80 48 d
Unit price
Rp 39,684 (est.)

Recommendation

  • 1.Forecast 9.8 EA/year: 9.8 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~29 days; expected demand during lead time 0.8.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 9, order up to 19.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 17 now.
  • 5.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
17 EA
Rp 674,628 · order by 01 Oct 2026
Expected arrival ≈ 29 days
Price estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
9
safety stock 9
Rec. Max
19
order qty 10
Service level
100.0%
stockout risk now 22%
Unit price
Rp 39,684
Category + unit estimate
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 72 days ago, 9 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 248.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~14 days.

Installed on 3 functional locations

1 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-886D
BOTTOM FAN
B141.43
PX_KC-538
REFLUX BLOWER
S2124.85
PX_KT-383A
TURBINE FOR KC-383A
S173.67

Lead time and procurement

Lead time 29 ± 17 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 Sept 2026LowPX_KC-886DKC-886D high vibration
24 Sept 2026EmergencyPX_KC-538KC-538 high vibration
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
16 Sept 2026EmergencyPX_KC-538Leak from packing
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
01 Sept 2026MediumPX_KC-538KC-538 lube oil filter DP high
01 Sept 2026MediumPX_KC-538KC-538 high vibration
23 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
19 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A

Recent goods issues

Posting dateQtyOrderOrder type
21 Jul 20263201000011349Corrective