O-RING,NBR,114MM ID,2.5MM CS

Material 4100020600 · O-RING · Plant 1000

AMaintainCritical insurance spare
Material
4100020600
Category
O-RING
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 5 FuncLocs A/B)
Supplier
No PO history
Lead time
29 d · P80 48 d
Unit price
Rp 39,684 (est.)

Recommendation

  • 1.Forecast 2.5 EA/year: 1.8 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~29 days; expected demand during lead time 0.1.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 9.
  • 4.No issue in 17 months, but it protects critical equipment: keep it.
  • 5.Installed on 5 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
9 / 0
no open PO
Today Min / Max
2 / 4
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
9
order qty 3
Service level
100.0%
stockout risk now 0%
Unit price
Rp 39,684
Category + unit estimate
ML early warning: 14% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 3 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 177.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 5 functional locations

2 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_KT-460B
TURBINE FOR KC-460B
A121.96
PX_KT-447
TURBINE FOR KC-447
S1136.24
PX_KT-264A
TURBINE FOR KC-264A
S142.39
PX_KT-875
TURBINE FOR KC-875
S101.10

Lead time and procurement

Lead time 29 ± 17 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
26 Dec 2026PX_KT-264ATurbine major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
20 Jul 2026LowPX_KT-856AFollow up after steam upset KT-856A
08 Jul 2026MediumPX_KT-447Replace lamp as per PM finding
11 Jun 2026LowPX_KT-264ALeak from packing
13 May 2026LowPX_KT-447KT-447 trip test
21 Apr 2026LowPX_KT-264AFollow up after steam upset KT-264A
19 Apr 2026LowPX_KT-447Follow up after steam upset KT-447
30 Mar 2026LowPX_KT-447Leak from packing
28 Mar 2026MediumPX_KT-447Follow up after steam upset KT-447
26 Mar 2026MediumPX_KT-856AKT-856A steam leak at gland

Recent goods issues

Never issued in the 17-month history.