O-RING,EPDM,67MM ID,3.5MM CS
Material 4100020710 · O-RING · Plant 1000
ASafety-criticalReduceNon-moving
- Material
- 4100020710
- Category
- O-RING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 3 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- No PO history
- Lead time
- 29 d · P80 48 d
- Unit price
- Rp 39,684 (est.)
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 0.6 EA/year: 0.6 unplanned (installed-base failure prior (no history)).
- 3.Lead time ~29 days; expected demand during lead time 0.0.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
- 5.Stock 8 exceeds the level to keep (6) by 2.
- 6.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
8 / 0
no open PO
Today Min / Max
5 / 9
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
6
order qty 3
Service level
100.0%
stockout risk now 0%
Unit price
Rp 39,684
Category + unit estimate
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 56.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.
Installed on 3 functional locations
2 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-854C FEED FAN | A | 1 | 7 | 2.28 |
| PX_KC-284A WASH WATER COMPRESSOR | B | 1 | 2 | 1.43 |
| PX_SDV-552D INHIBITOR ISOLATION | S | 1 | 2 | 0.91 |
Lead time and procurement
Lead time 29 ± 17 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 22 Sept 2026 | Medium | PX_KC-854C | Overhaul |
| 29 Jul 2026 | Medium | PX_KC-854C | Install scaffolding at KC-854C |
| 17 Jul 2026 | Low | PX_KC-854C | Painting KC-854C |
| 13 Mar 2026 | Medium | PX_KC-854C | KC-854C bearing temp high |
| 22 Nov 2025 | Medium | PX_KC-854C | KC-854C lube oil filter DP high |
| 09 Oct 2025 | Medium | PX_SDV-552D | SDV-552D fail to close |
| 14 Sept 2025 | Medium | PX_KC-854C | [MSI-B-25-TSW-309] Permanent repair |
| 04 Sept 2025 | Medium | PX_KC-284A | KC-284A lube oil filter DP high |
| 19 Jul 2025 | Medium | PX_SDV-552D | SDV-552D solenoid burnt |
| 08 Jul 2025 | Medium | PX_KC-284A | KC-284A high vibration |
Recent goods issues
Never issued in the 17-month history.