O-RING,EPDM,68MM ID,5.3MM CS

Material 4100021749 · O-RING · Plant 1000

AReorderNormalSlow-moving
Material
4100021749
Category
O-RING
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 3 FuncLocs A/B)
Supplier
DUTA TEKNOLOGI ABADI PT
Lead time
29 d · P80 48 d
Unit price
Rp 26,482

Recommendation

  • 1.Forecast 5.8 EA/year: 5.8 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~29 days; expected demand during lead time 0.5.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 12.
  • 4.On hand 2 + on order 1 is at or below the reorder point: order 9 now.
  • 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
9 EA
Rp 238,338 · order by 01 Oct 2026
Expected arrival ≈ 29 days
Single sourceOpen PO
On hand / on order
2 / 1
next delivery 10 Oct 2026
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
12
order qty 6
Service level
99.9%
stockout risk now 1%
Unit price
Rp 26,482
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 183 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 580.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 3 functional locations

2 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_PP-1216C
FLUSHING OIL PUMP
B100.19
PX_KT-202
TURBINE FOR KC-202
S142.81

Lead time and procurement

Lead time 29 ± 17 days (PO history + category, 1 PO lines) · on-time 60%

PR dateTypeQtyUnit priceDeliveryLead time
11 Sept 2026PR06
Regular replenishment
1Rp 26,48210 Oct 2026
open
29 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
03 Apr 2026MediumPX_KT-419AKT-419A steam leak at gland
17 Mar 2026MediumPX_KT-419AInstall cover plate for MCP cracking
09 Jan 2026MediumPX_KT-202KT-202 governor valve hunting
20 Nov 2025MediumPX_KT-419ALeak from packing
10 Nov 2025MediumPX_KT-419APainting KT-419A
17 Sept 2025MediumPX_KT-202Replace lamp as per PM finding
03 Sept 2025MediumPX_KT-419AFollow up after steam upset KT-419A
06 Jul 2025LowPX_KT-202KT-202 steam leak at gland
15 May 2025LowPX_KT-419APSM25/Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
01 Apr 20263201000012873Corrective