Sparely
DU

STUDBOLT,5/8INX115MM,B8M/8M

Material 4100024203 · STUDBOLT · Plant 1000

ASafety-criticalReorderNormalBelow reorder point
Material
4100024203
Category
STUDBOLT
Base unit
EA
MRP type
Stock Item
Criticality
A (57 of 101 FuncLocs A/B, 6 safety/shutdown valve)
Supplier
SURYA PERKASA GLOBAL PT
Lead time
38 d · P80 55 d
Unit price
Rp 48,658

Recommendation

  • 1.Safety-critical element: installed on 6 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 1,445 EA/year: 1,439 unplanned (recency-weighted compound poisson (own history)) + 5.7 from the maintenance plan.
  • 3.Lead time ~38 days; expected demand during lead time 150.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 545, order up to 1,213.
  • 5.On hand 390 + on order 0 is at or below the reorder point: order 823 now.
  • 6.Installed on 101 FuncLoc(s), 57 of them criticality A/B.
  • 7.ML early warning: 100% probability of demand in the next 90 days.
Proposed purchase requisition
823 EA
Rp 40.0M · order by 01 Oct 2026
Expected arrival ≈ 38 days
Safety-critical (SCE)ML early warningLast turnaround used 612Single sourceAbnormal consumption
On hand / on order
390 / 0
no open PO
Today Min / Max
464 / 1,158
static parameters in BoM
Rec. Min (reorder point)
545
safety stock 395
Rec. Max
1,213
order qty 668
Service level
99.9%
stockout risk now 3%
Unit price
Rp 48,658
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 20 issue days in the last 180 days, last issue 3 days ago, 67 failure notifications on its equipment in 90 days, 2 planned jobs in 90 days, 6 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (684 units) excluded from the baseline.

Demand pattern Erratic · 61 issue days · 2 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 8.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.

Installed on 101 functional locations

57 with criticality A/B · 1,412 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-105
CRACKING FURNACE BF-105
A2411442.86
PX_BF-106
CRACKING FURNACE BF-106
A248230.86
PX_BF-109
CRACKING FURNACE BF-109
A242911.58
PX_KC-226
HYDROGEN AIR COMPRESSOR
A2062.28
PX_PP-888A
CONDENSATE PUMP
A461.90
PX_KC-222B
LEAN AMINE COMPRESSOR
A1651.85
PX_KT-397A
TURBINE FOR KC-397A
A1652.81
PX_KC-396
WASH WATER BLOWER
A431.43
PX_CL-859
FLUSHING OIL SCRUBBER
A1220.81
PX_KC-391D
QUENCH WATER COMPRESSOR
A1221.43
PX_KT-460B
TURBINE FOR KC-460B
A1621.96
PX_KT-513
TURBINE FOR KC-513
A421.53

Lead time and procurement

Lead time 38 ± 21 days (PO history, 21 PO lines) · on-time 49%

PR dateTypeQtyUnit priceDeliveryLead time
05 Aug 2026PR03
Regular replenishment
575Rp 47,93331 Aug 202626 d
16 Jul 2026PR03
Regular replenishment
914Rp 48,50316 Aug 202631 d
15 Jun 2026PR06
Regular replenishment
1,274Rp 50,15609 Aug 202655 d
30 May 2026PR04
Regular (other)
1,076Rp 48,65804 Jul 202635 d
25 Apr 2026PR03
Regular replenishment
1,249Rp 50,23708 May 202613 d
19 Apr 2026PR03
Regular replenishment
1,181Rp 47,97211 May 202622 d
28 Mar 2026PR06
Regular replenishment
468Rp 49,28913 Apr 202616 d
06 Mar 2026PR03
Regular replenishment
659Rp 50,24323 Apr 202648 d
31 Jan 2026PR03
Regular replenishment
1,195Rp 47,11417 Feb 202617 d
29 Jan 2026PR06
Regular replenishment
1,177Rp 47,18820 Feb 202622 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Dec 2026PY_FCV-1410BFinal Element Overhaul; Control Valve2.86
26 Dec 2026PX_KT-264ATurbine major overhaul2.86

Recent notifications on its equipment

DatePriorityFuncLocDescription
29 Sept 2026HighPX_BF-105Repair refractory crack BF-105
29 Sept 2026MediumPX_BF-106Decoking follow up BF-106
29 Sept 2026MediumPX_BF-106Decoking follow up BF-106
28 Sept 2026LowPX_BF-106Peep door broken BF-106
28 Sept 2026LowPX_KC-886DKC-886D high vibration
26 Sept 2026MediumPX_KC-396Replace lamp as per PM finding
22 Sept 2026LowPX_HE-113DRetubing HE-113D
22 Sept 2026MediumPX_PP-888AOil leak at PP-888A bearing housing
20 Sept 2026MediumPX_BF-105Replace lamp as per PM finding
20 Sept 2026MediumPX_BF-105Install scaffolding at BF-105

Recent goods issues

Posting dateQtyOrderOrder type
28 Sept 202648201000013476Corrective
25 Sept 202696209000029477Other maintenance
25 Aug 202696201000039454Corrective
23 Aug 20264201000002237Corrective
19 Aug 202624201000015475Corrective
04 Aug 20268201000010969Corrective
31 Jul 202616204000016683Preventive
27 Jul 202696201000029643Corrective
19 Jul 202632204000022669Preventive
19 Jul 20268204000022669Preventive
13 Jul 202612201000024244Corrective
13 Jul 202632201000034553Corrective
06 Jul 202636209000029244Other maintenance
04 Jul 202648201000009511Corrective
26 Jun 202632201000021992Corrective