STUDBOLT,5/8INX45MM,B16/4
Material 4100024318 · STUDBOLT · Plant 1000
ASafety-criticalMonitorHealthy
- Material
- 4100024318
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (24 of 35 FuncLocs A/B, 2 safety/shutdown valve)
- Supplier
- KARYA UTAMA GLOBAL PT
- Lead time
- 30 d · P80 38 d
- Unit price
- Rp 40,546
Recommendation
- 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 585 EA/year: 565 unplanned (recency-weighted compound poisson (own history)) + 20 from the maintenance plan.
- 3.Lead time ~30 days; expected demand during lead time 46.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 193, order up to 659.
- 5.Installed on 35 FuncLoc(s), 24 of them criticality A/B.
- 6.ML early warning: 99% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningLast turnaround used 324Single sourceAbnormal consumptionOpen PO
On hand / on order
527 / 741
next delivery 08 Oct 2026
Today Min / Max
325 / 730
static parameters in BoM
Rec. Min (reorder point)
193
safety stock 147
Rec. Max
659
order qty 466
Service level
100.0%
stockout risk now 0%
Unit price
Rp 40,546
PO history
ML early warning: 99% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 8 issue days in the last 180 days, last issue 1 days ago, 58 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 4 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (336 units) excluded from the baseline.
Demand pattern Erratic · 24 issue days · 4 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 4.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 35 functional locations
24 with criticality A/B · 492 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 8 | 114 | 42.86 |
| PX_BF-112 CRACKING FURNACE BF-112 | A | 8 | 73 | 27.01 |
| PX_BF-102 CRACKING FURNACE BF-102 | A | 16 | 71 | 28.72 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 24 | 23 | 9.01 |
| PX_KT-856A TURBINE FOR KC-856A | A | 20 | 7 | 2.81 |
| PX_HE-1903 RICH AMINE CONDENSER | A | 16 | 2 | 1.08 |
| PX_HE-884B RECYCLE ETHANE TLE | A | 20 | 2 | 1.08 |
| PX_CL-573 SLOP OIL STRIPPER | A | 16 | 0 | 0.38 |
| PX_FCV-885 CONTROL VALVE | A | 12 | 0 | 0.11 |
| PX_HE-1108C INHIBITOR TLE | A | 16 | 0 | 0.22 |
| PX_HE-584B FEED PREHEATER | A | 16 | 0 | 0.22 |
| PX_KC-223 RECYCLE ETHANE FAN | A | 12 | 0 | 0.57 |
Lead time and procurement
Lead time 30 ± 17 days (PO history, 7 PO lines) · on-time 45%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 11 Sept 2026 | PR03 Regular replenishment | 216 | Rp 39,935 | 08 Oct 2026 open | 27 d |
| 04 Aug 2026 | PR03 Regular replenishment | 525 | Rp 41,712 | 09 Oct 2026 open | 66 d |
| 24 Jul 2026 | PR03 Regular replenishment | 532 | Rp 40,647 | 13 Aug 2026 | 20 d |
| 09 May 2026 | PR03 Regular replenishment | 363 | Rp 40,626 | 21 May 2026 | 12 d |
| 07 Dec 2025 | PR03 Regular replenishment | 335 | Rp 39,973 | 14 Jan 2026 | 38 d |
| 11 May 2025 | PR03 Regular replenishment | 403 | Rp 40,546 | 11 Jun 2025 | 31 d |
| 05 May 2025 | PR03 Regular replenishment | 473 | Rp 39,765 | 10 Jun 2025 | 36 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 26 Dec 2026 | PX_KT-264A | Turbine major overhaul | 17.2 |
| 01 Jan 2027 | PX_PP-508D | Pump overhaul | 2.86 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
| 20 Sept 2026 | Medium | PX_BF-105 | Replace lamp as per PM finding |
| 20 Sept 2026 | Medium | PX_BF-105 | Install scaffolding at BF-105 |
| 17 Sept 2026 | Medium | PX_BF-112 | Cleaning burner BF-112 |
| 17 Sept 2026 | Medium | PX_PP-411A | Replace bearing PP-411A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Sept 2026 | 32 | 201000012524 | Corrective |
| 23 Sept 2026 | 32 | 201000033998 | Corrective |
| 03 Sept 2026 | 24 | 201000019996 | Corrective |
| 22 Aug 2026 | 96 | 201000037361 | Corrective |
| 22 Aug 2026 | 8 | 201000037361 | Corrective |
| 03 Aug 2026 | 96 | 201000031536 | Corrective |
| 06 Jun 2026 | 96 | 201000026445 | Corrective |
| 08 May 2026 | 12 | 201000013320 | Corrective |
| 06 Apr 2026 | 16 | 201000039783 | Corrective |
| 17 Mar 2026 | 24 | 201000018051 | Corrective |
| 26 Feb 2026 | 4 | 201000005836 | Corrective |
| 05 Feb 2026 | 48 | 201000030018 | Corrective |
| 31 Jan 2026 | 12 | 201000018506 | Corrective |
| 18 Jan 2026 | 4 | 201000026755 | Corrective |
| 15 Jan 2026 | 4 | 201000002562 | Corrective |