STUDBOLT,1INX40MM,B8M/8M
Material 4100024353 · STUDBOLT · Plant 1000
ASafety-criticalReduceExcess
- Material
- 4100024353
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (14 of 22 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- SURYA INSTRUMEN MAKMUR PT
- Lead time
- 36 d · P80 68 d
- Unit price
- Rp 38,891
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 264 EA/year: 264 unplanned (recency-weighted compound poisson (own history)).
- 3.Lead time ~36 days; expected demand during lead time 26.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 130, order up to 394.
- 5.Stock 853 exceeds the level to keep (456) by 397; the level includes the 456 used in the last turnaround.
- 6.Installed on 22 FuncLoc(s), 14 of them criticality A/B.
- 7.ML early warning: 90% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningLast turnaround used 456Single sourceOpen PO
On hand / on order
853 / 348
next delivery 05 Dec 2026
Today Min / Max
305 / 648
static parameters in BoM
Rec. Min (reorder point)
130
safety stock 104
Rec. Max
394
order qty 264
Service level
99.9%
stockout risk now 0%
Unit price
Rp 38,891
PO history
ML early warning: 90% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 5 issue days in the last 180 days, last issue 67 days ago, 17 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (744 units) excluded from the baseline.
Demand pattern Lumpy · 15 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 22 functional locations
14 with criticality A/B · 312 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-107 CRACKING FURNACE BF-107 | A | 16 | 23 | 9.01 |
| PX_PP-1864 FUEL OIL PUMP | A | 24 | 6 | 2.33 |
| PX_KT-397A TURBINE FOR KC-397A | A | 16 | 5 | 2.81 |
| PX_KT-513 TURBINE FOR KC-513 | A | 12 | 2 | 1.53 |
| PX_KC-155D CAUSTIC BLOWER | A | 24 | 0 | 0.57 |
| PX_TCV-546 PP-1168A TEMP CONTROL | A | 8 | 0 | 0.12 |
| PY_PRV-1355 SAFETY VALVE PP-912B | A | 4 | 0 | 0.04 |
| PX_PP-1320D INHIBITOR PUMP | B | 24 | 11 | 4.47 |
| PX_CL-1326 SEAL OIL STRIPPER | B | 4 | 5 | 1.23 |
| PX_KC-853D SLOP OIL COMPRESSOR | B | 8 | 4 | 1.85 |
| PX_HE-1560A QUENCH OIL EXCHANGER | B | 8 | 0 | 0.22 |
| PX_HE-1741B SPENT CAUSTIC COOLER | B | 16 | 0 | 0.22 |
Lead time and procurement
Lead time 36 ± 22 days (PO history, 10 PO lines) · on-time 34%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 21 Sept 2026 | PR04 Regular (other) | 348 | Rp 39,194 | 05 Dec 2026 open | 75 d |
| 03 Jul 2026 | PR06 Regular replenishment | 422 | Rp 38,017 | 27 Jul 2026 | 24 d |
| 22 Mar 2026 | PR03 Regular replenishment | 397 | Rp 40,834 | 31 May 2026 | 70 d |
| 31 Jan 2026 | PR06 Regular replenishment | 196 | Rp 38,833 | 07 Feb 2026 | 7 d |
| 27 Jan 2026 | PR06 Regular replenishment | 218 | Rp 38,104 | 01 Mar 2026 | 33 d |
| 02 Nov 2025 | PR03 Regular replenishment | 531 | Rp 38,948 | 03 Dec 2025 | 31 d |
| 03 Sept 2025 | PR06 Regular replenishment | 485 | Rp 40,309 | 10 Nov 2025 | 68 d |
| 20 Jun 2025 | PR06 Regular replenishment | 391 | Rp 40,505 | 05 Aug 2025 | 46 d |
| 14 Jun 2025 | PR06 Regular replenishment | 376 | Rp 37,859 | 28 Jun 2025 | 14 d |
| 12 Jun 2025 | PR06 Regular replenishment | 282 | Rp 38,427 | 13 Jul 2025 | 31 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_PP-1864 | Install scaffolding at PP-1864 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 17 Sept 2026 | Medium | PX_HE-1396C | [MSI-B-26-NWH-385] Permanent repair |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 08 Sept 2026 | Medium | PX_BF-107 | Replace lamp as per PM finding |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 01 Sept 2026 | Low | PX_KT-447 | Replace lamp as per PM finding |
| 26 Aug 2026 | High | PX_CL-1326 | Install scaffolding at CL-1326 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 26 Jul 2026 | 24 | 201000002237 | Corrective |
| 16 May 2026 | 4 | 201000026522 | Corrective |
| 24 Apr 2026 | 4 | 201000008643 | Corrective |
| 15 Apr 2026 | 24 | 205000002255 | Other maintenance |
| 11 Apr 2026 | 8 | 201000005759 | Corrective |
| 22 Jan 2026 | 12 | 201000032157 | Corrective |
| 16 Jan 2026 | 144 | 203000029956 | Turnaround |
| 05 Jan 2026 | 32 | 201000039015 | Corrective |
| 03 Jan 2026 | 48 | 201000014819 | Corrective |
| 27 Dec 2025 | 24 | 203000016277 | Turnaround |
| 11 Dec 2025 | 8 | 201000001970 | Corrective |
| 16 Nov 2025 | 8 | 201000039953 | Corrective |
| 15 Nov 2025 | 288 | 203000023445 | Turnaround |
| 03 Nov 2025 | 24 | 201000004143 | Corrective |
| 05 Sept 2025 | 96 | 201000027203 | Corrective |