Sparely
DU

STUDBOLT,1INX40MM,B8M/8M

Material 4100024353 · STUDBOLT · Plant 1000

ASafety-criticalReduceExcess
Material
4100024353
Category
STUDBOLT
Base unit
EA
MRP type
Stock Item
Criticality
A (14 of 22 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
SURYA INSTRUMEN MAKMUR PT
Lead time
36 d · P80 68 d
Unit price
Rp 38,891

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 264 EA/year: 264 unplanned (recency-weighted compound poisson (own history)).
  • 3.Lead time ~36 days; expected demand during lead time 26.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 130, order up to 394.
  • 5.Stock 853 exceeds the level to keep (456) by 397; the level includes the 456 used in the last turnaround.
  • 6.Installed on 22 FuncLoc(s), 14 of them criticality A/B.
  • 7.ML early warning: 90% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningLast turnaround used 456Single sourceOpen PO
On hand / on order
853 / 348
next delivery 05 Dec 2026
Today Min / Max
305 / 648
static parameters in BoM
Rec. Min (reorder point)
130
safety stock 104
Rec. Max
394
order qty 264
Service level
99.9%
stockout risk now 0%
Unit price
Rp 38,891
PO history
ML early warning: 90% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 5 issue days in the last 180 days, last issue 67 days ago, 17 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (744 units) excluded from the baseline.

Demand pattern Lumpy · 15 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.

Installed on 22 functional locations

14 with criticality A/B · 312 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-107
CRACKING FURNACE BF-107
A16239.01
PX_PP-1864
FUEL OIL PUMP
A2462.33
PX_KT-397A
TURBINE FOR KC-397A
A1652.81
PX_KT-513
TURBINE FOR KC-513
A1221.53
PX_KC-155D
CAUSTIC BLOWER
A2400.57
PX_TCV-546
PP-1168A TEMP CONTROL
A800.12
PY_PRV-1355
SAFETY VALVE PP-912B
A400.04
PX_PP-1320D
INHIBITOR PUMP
B24114.47
PX_CL-1326
SEAL OIL STRIPPER
B451.23
PX_KC-853D
SLOP OIL COMPRESSOR
B841.85
PX_HE-1560A
QUENCH OIL EXCHANGER
B800.22
PX_HE-1741B
SPENT CAUSTIC COOLER
B1600.22

Lead time and procurement

Lead time 36 ± 22 days (PO history, 10 PO lines) · on-time 34%

PR dateTypeQtyUnit priceDeliveryLead time
21 Sept 2026PR04
Regular (other)
348Rp 39,19405 Dec 2026
open
75 d
03 Jul 2026PR06
Regular replenishment
422Rp 38,01727 Jul 202624 d
22 Mar 2026PR03
Regular replenishment
397Rp 40,83431 May 202670 d
31 Jan 2026PR06
Regular replenishment
196Rp 38,83307 Feb 20267 d
27 Jan 2026PR06
Regular replenishment
218Rp 38,10401 Mar 202633 d
02 Nov 2025PR03
Regular replenishment
531Rp 38,94803 Dec 202531 d
03 Sept 2025PR06
Regular replenishment
485Rp 40,30910 Nov 202568 d
20 Jun 2025PR06
Regular replenishment
391Rp 40,50505 Aug 202546 d
14 Jun 2025PR06
Regular replenishment
376Rp 37,85928 Jun 202514 d
12 Jun 2025PR06
Regular replenishment
282Rp 38,42713 Jul 202531 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026MediumPX_PP-1864Install scaffolding at PP-1864
24 Sept 2026LowPX_BF-107Install scaffolding at BF-107
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
17 Sept 2026MediumPX_HE-1396C[MSI-B-26-NWH-385] Permanent repair
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
08 Sept 2026MediumPX_BF-107Replace lamp as per PM finding
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
26 Aug 2026HighPX_CL-1326Install scaffolding at CL-1326

Recent goods issues

Posting dateQtyOrderOrder type
26 Jul 202624201000002237Corrective
16 May 20264201000026522Corrective
24 Apr 20264201000008643Corrective
15 Apr 202624205000002255Other maintenance
11 Apr 20268201000005759Corrective
22 Jan 202612201000032157Corrective
16 Jan 2026144203000029956Turnaround
05 Jan 202632201000039015Corrective
03 Jan 202648201000014819Corrective
27 Dec 202524203000016277Turnaround
11 Dec 20258201000001970Corrective
16 Nov 20258201000039953Corrective
15 Nov 2025288203000023445Turnaround
03 Nov 202524201000004143Corrective
05 Sept 202596201000027203Corrective