STUDBOLT,5/8INX30MM,B16/4

Material 4100024362 · STUDBOLT · Plant 1000

ASafety-criticalReduceExcess
Material
4100024362
Category
STUDBOLT
Base unit
EA
MRP type
Stock Item
Criticality
A (13 of 27 FuncLocs A/B, 3 safety/shutdown valve)
Supplier
ANUGRAH SARANA JAYA PT
Lead time
28 d · P80 42 d
Unit price
Rp 24,282

Recommendation

  • 1.Safety-critical element: installed on 3 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 336 EA/year: 322 unplanned (recency-weighted compound poisson (own history)) + 14 from the maintenance plan.
  • 3.Lead time ~28 days; expected demand during lead time 25.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 122, order up to 459.
  • 5.Stock 571 exceeds the level to keep (459) by 112.
  • 6.Installed on 27 FuncLoc(s), 13 of them criticality A/B.
  • 7.ML early warning: 96% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningLast turnaround used 24Single sourceAbnormal consumption
On hand / on order
571 / 0
no open PO
Today Min / Max
188 / 503
static parameters in BoM
Rec. Min (reorder point)
122
safety stock 98
Rec. Max
459
order qty 337
Service level
99.9%
stockout risk now 0%
Unit price
Rp 24,282
PO history
ML early warning: 96% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 6 issue days in the last 180 days, last issue 9 days ago, 22 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (336 units) excluded from the baseline.

Demand pattern Lumpy · 18 issue days · 3 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.

Installed on 27 functional locations

13 with criticality A/B · 372 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-107
CRACKING FURNACE BF-107
A4239.01
PX_CL-961
LEAN AMINE COLUMN
A2431.23
PX_HE-1975
HYDROGEN COOLER
A831.50
PX_KC-396
WASH WATER BLOWER
A1231.43
PX_HE-492C
CONDENSATE TLE
A2410.22
PX_PP-1766A
ETHYLENE PUMP
A410.19
PX_HE-694C
LEAN AMINE CONDENSER
B820.65
PX_PP-1253B
LUBE OIL PUMP
B420.62
PX_HE-1647D
BOTTOM COOLER
B400.22
PX_HE-526A
COOLING WATER REBOILER
B1600.22
PX_PRV-248
SAFETY VALVE VD-1282
B800.04
PX_VD-1525B
SEAL OIL SURGE DRUM
B400.08

Lead time and procurement

Lead time 28 ± 13 days (PO history, 9 PO lines) · on-time 60%

PR dateTypeQtyUnit priceDeliveryLead time
28 Jun 2026PR03
Regular replenishment
384Rp 23,91701 Aug 202634 d
15 Jun 2026PR03
Regular replenishment
389Rp 23,98722 Jul 202637 d
24 Feb 2026PR06
Regular replenishment
377Rp 25,11914 Apr 202649 d
31 Jan 2026PR03
Regular replenishment
273Rp 23,93722 Feb 202622 d
17 Dec 2025PR03
Regular replenishment
209Rp 24,69905 Jan 202619 d
13 Nov 2025PR03
Regular replenishment
253Rp 25,19501 Jan 202649 d
29 Jul 2025PR06
Regular replenishment
309Rp 24,92915 Aug 202517 d
09 Jul 2025PR03
Regular replenishment
152Rp 24,10602 Aug 202524 d
04 Jul 2025PR03
Regular replenishment
295Rp 24,45723 Jul 202519 d
22 May 2025PR03
Regular replenishment
209Rp 23,90820 Apr 20251 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Dec 2026PX_TCV-1082AFinal Element Overhaul; Control Valve14.3

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026MediumPX_KC-396Replace lamp as per PM finding
24 Sept 2026LowPX_BF-107Install scaffolding at BF-107
21 Sept 2026MediumPX_BF-110Replace burner tip BF-110
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
17 Sept 2026MediumPX_BF-110Install scaffolding at BF-110
15 Sept 2026MediumPX_BF-110Decoking follow up BF-110
11 Sept 2026MediumPX_BF-110Leak from packing
11 Sept 2026MediumPX_CL-961[MSI-B-26-UAX-291] Permanent repair
08 Sept 2026MediumPX_BF-107Replace lamp as per PM finding
03 Sept 2026LowPX_BF-110Hot spot at convection BF-110

Recent goods issues

Posting dateQtyOrderOrder type
22 Sept 202612201000037585Corrective
08 Sept 20268201000002044Corrective
24 Jun 202636209000014083Other maintenance
16 Jun 202616201000018563Corrective
11 May 202616201000016405Corrective
05 Apr 20264205000036120Other maintenance
14 Mar 20268201000021409Corrective
30 Jan 202696201000025995Corrective
14 Jan 202624201000020496Corrective
13 Jan 202632201000020496Corrective
29 Dec 202524203000006078Turnaround
25 Dec 202524201000034498Corrective
25 Dec 202548201000037770Corrective
15 Dec 202596201000022685Corrective
25 Nov 202548201000018405Corrective