STUDBOLT,3/4INX85MM,B8M/8M
Material 4100024532 · STUDBOLT · Plant 1000
AReduceExcess
- Material
- 4100024532
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (16 of 21 FuncLocs A/B)
- Supplier
- SAMUDRA SEJAHTERA INTERNASIONAL PT
- Lead time
- 26 d · P80 37 d
- Unit price
- Rp 28,479
Recommendation
- 1.Forecast 238 EA/year: 226 unplanned (recency-weighted compound poisson (own history)) + 11 from the maintenance plan.
- 2.Lead time ~26 days; expected demand during lead time 16.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 123, order up to 361.
- 4.Stock 445 exceeds the level to keep (361) by 84.
- 5.Installed on 21 FuncLoc(s), 16 of them criticality A/B.
- 6.ML early warning: 63% probability of demand in the next 90 days.
ML early warningSingle sourceAbnormal consumption
On hand / on order
445 / 0
no open PO
Today Min / Max
155 / 409
static parameters in BoM
Rec. Min (reorder point)
123
safety stock 108
Rec. Max
361
order qty 238
Service level
99.9%
stockout risk now 0%
Unit price
Rp 28,479
PO history
ML early warning: 63% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 78 days ago, 8 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (132 units) excluded from the baseline.
Demand pattern Lumpy · 10 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 21 functional locations
16 with criticality A/B · 292 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-107 CRACKING FURNACE BF-107 | A | 12 | 23 | 9.01 |
| PX_KT-513 TURBINE FOR KC-513 | A | 16 | 2 | 1.53 |
| PX_HE-1305B FEED CONDENSER | A | 12 | 1 | 0.22 |
| PX_HE-826D GASOLINE CONDENSER | A | 20 | 0 | 0.22 |
| PX_KC-527 METHANOL BLOWER | A | 24 | 0 | 0.57 |
| PX_PCV-1113 BY PASS DUCT | A | 8 | 0 | 0.08 |
| PX_PCV-935 KC-582B PRESSURE CONTROL | A | 12 | 0 | 0.08 |
| PX_PP-556A LEAN AMINE PUMP | A | 16 | 0 | 0.19 |
| PY_HE-1501B RECYCLE ETHANE TLE | A | 20 | 0 | 0.22 |
| PY_VD-1188 LUBE OIL KO DRUM | A | 12 | 0 | 0.08 |
| PX_PCV-1103 PRESSURE CONTROL VALVE | B | 4 | 3 | 0.51 |
| PX_FCV-1853 VD-1252 OUTLET FLOW | B | 8 | 0 | 0.11 |
Lead time and procurement
Lead time 26 ± 12 days (PO history, 9 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 01 Jul 2026 | PR03 Regular replenishment | 120 | Rp 27,697 | 09 Aug 2026 | 39 d |
| 20 Feb 2026 | PR03 Regular replenishment | 70 | Rp 27,758 | 02 Mar 2026 | 10 d |
| 31 Jan 2026 | PR03 Regular replenishment | 140 | Rp 28,042 | 19 Feb 2026 | 19 d |
| 05 Dec 2025 | PR03 Regular replenishment | 206 | Rp 28,933 | 22 Dec 2025 | 17 d |
| 28 Nov 2025 | PR03 Regular replenishment | 78 | Rp 28,479 | 23 Dec 2025 | 25 d |
| 05 Oct 2025 | PR06 Regular replenishment | 201 | Rp 27,541 | 06 Nov 2025 | 32 d |
| 08 Sept 2025 | PR03 Regular replenishment | 76 | Rp 28,972 | 25 Sept 2025 | 17 d |
| 29 Jun 2025 | PR06 Regular replenishment | 116 | Rp 28,538 | 04 Aug 2025 | 36 d |
| 04 May 2025 | PR05 Project / turnaround | 238 | Rp 29,361 | 15 Jun 2025 | 42 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Nov 2026 | PX_PP-556A | Pump overhaul | 11.5 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 08 Sept 2026 | Medium | PX_BF-107 | Replace lamp as per PM finding |
| 15 Aug 2026 | Medium | PX_BF-107 | Hot spot at convection BF-107 |
| 08 Aug 2026 | Low | PX_BF-107 | Cleaning burner BF-107 |
| 21 Jul 2026 | Medium | PX_BF-107 | Replace lamp as per PM finding |
| 21 Jul 2026 | Medium | PX_BF-107 | Thermograph wall BF-107 |
| 18 Jul 2026 | Emergency | PX_BF-107 | Hot spot at convection BF-107 |
| 15 Jul 2026 | Medium | PX_KT-624A | [MSI-B-26-RXR-331/M] Replace line |
| 10 Jul 2026 | Medium | PX_BF-107 | Hot spot at convection BF-107 |
| 26 Jun 2026 | Medium | PX_PCV-1103 | PCV-1103; IA leak from regulator |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 15 Jul 2026 | 96 | 201000025691 | Corrective |
| 31 Jan 2026 | 32 | 201000003094 | Corrective |
| 25 Jan 2026 | 12 | 204000016196 | Preventive |
| 29 Dec 2025 | 16 | 201000039652 | Corrective |
| 10 Dec 2025 | 4 | 201000037297 | Corrective |
| 03 Dec 2025 | 48 | 201000008508 | Corrective |
| 03 Dec 2025 | 96 | 201000026150 | Corrective |
| 11 Nov 2025 | 4 | 201000030986 | Corrective |
| 22 Sept 2025 | 36 | 203000003244 | Turnaround |
| 07 Sept 2025 | 32 | 201000005017 | Corrective |
| 26 Aug 2025 | 8 | 201000009464 | Corrective |
| 24 Aug 2025 | 72 | 203000020904 | Turnaround |
| 15 Jul 2025 | 24 | 203000031669 | Turnaround |
| 03 Jul 2025 | 48 | 201000006950 | Corrective |
| 24 Jun 2025 | 32 | 201000006217 | Corrective |