STUDBOLT,1INX45MM,B16/4
Material 4100024534 · STUDBOLT · Plant 1000
ASafety-criticalReorderNormalBelow reorder point
- Material
- 4100024534
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (14 of 19 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- RAJAWALI INSTRUMEN INTERNASIONAL PT
- Lead time
- 23 d · P80 29 d
- Unit price
- Rp 95,608
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 249 EA/year: 240 unplanned (recency-weighted compound poisson (own history)) + 8.6 from the maintenance plan.
- 3.Lead time ~23 days; expected demand during lead time 15.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 84, order up to 282.
- 5.On hand 48 + on order 0 is at or below the reorder point: order 234 now.
- 6.Installed on 19 FuncLoc(s), 14 of them criticality A/B.
- 7.ML early warning: 78% probability of demand in the next 90 days.
Proposed purchase requisition
234 EA
Rp 22.4M · order by 01 Oct 2026
Expected arrival ≈ 23 days
Safety-critical (SCE)ML early warningLast turnaround used 36Single sourceAbnormal consumption
On hand / on order
48 / 0
no open PO
Today Min / Max
42 / 75
static parameters in BoM
Rec. Min (reorder point)
84
safety stock 70
Rec. Max
282
order qty 198
Service level
99.9%
stockout risk now 4%
Unit price
Rp 95,608
PO history
ML early warning: 78% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 72 days ago, 25 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (60 units) excluded from the baseline.
Demand pattern Lumpy · 17 issue days · 2 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 19 functional locations
14 with criticality A/B · 268 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 24 | 114 | 42.86 |
| PX_KT-419A TURBINE FOR KC-419A | A | 12 | 6 | 2.81 |
| PX_KC-316D METHANOL FAN | A | 24 | 5 | 1.43 |
| PX_KT-397A TURBINE FOR KC-397A | A | 20 | 5 | 2.81 |
| PX_CL-1039 CHARGE GAS STRIPPER | A | 24 | 2 | 0.81 |
| PX_KC-435A FUEL OIL AIR COMPRESSOR | A | 20 | 2 | 1.00 |
| PX_HE-322C LEAN AMINE EXCHANGER | A | 8 | 0 | 0.22 |
| PY_VD-383 QUENCH OIL SURGE DRUM | A | 24 | 0 | 0.08 |
| PX_HE-786 ETHYLENE COOLER | B | 20 | 4 | 1.08 |
| PX_HE-1164D QUENCH WATER CONDENSER | B | 4 | 2 | 1.08 |
| PX_PP-1253B LUBE OIL PUMP | B | 8 | 2 | 0.62 |
| PX_PP-1577D ETHYLENE PUMP | B | 12 | 2 | 1.05 |
Lead time and procurement
Lead time 23 ± 10 days (PO history, 11 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 20 Jun 2026 | PR03 Regular replenishment | 114 | Rp 99,604 | 10 Jul 2026 | 20 d |
| 24 Mar 2026 | PR03 Regular replenishment | 72 | Rp 98,185 | 13 Apr 2026 | 20 d |
| 14 Feb 2026 | PR03 Regular replenishment | 186 | Rp 95,608 | 04 Mar 2026 | 18 d |
| 07 Feb 2026 | PR03 Regular replenishment | 128 | Rp 92,988 | 18 Feb 2026 | 11 d |
| 31 Jan 2026 | PR03 Regular replenishment | 159 | Rp 92,376 | 07 Mar 2026 | 35 d |
| 02 Nov 2025 | PR06 Regular replenishment | 241 | Rp 98,367 | 12 Nov 2025 | 10 d |
| 16 Oct 2025 | PR03 Regular replenishment | 187 | Rp 94,793 | 14 Nov 2025 | 29 d |
| 22 Sept 2025 | PR01 Import / long-lead | 92 | Rp 91,980 | 21 Oct 2025 | 29 d |
| 01 Sept 2025 | PR05 Project / turnaround | 164 | Rp 94,422 | 09 Oct 2025 | 38 d |
| 17 Jul 2025 | PR03 Regular replenishment | 69 | Rp 95,746 | 03 Aug 2025 | 17 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 26 Dec 2026 | PX_KT-264A | Turbine major overhaul | 8.59 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 20 Sept 2026 | Medium | PX_BF-105 | Replace lamp as per PM finding |
| 20 Sept 2026 | Medium | PX_BF-105 | Install scaffolding at BF-105 |
| 16 Sept 2026 | Medium | PX_HE-786 | Leak from packing |
| 14 Sept 2026 | Low | PX_BF-105 | Install cover plate BF-105 |
| 13 Sept 2026 | Medium | PX_BF-105 | Thermograph wall BF-105 |
| 07 Sept 2026 | Medium | PX_PP-1577D | Replace bearing PP-1577D |
| 06 Sept 2026 | Medium | PX_BF-105 | Repair insulation BF-105 |
| 01 Sept 2026 | Low | PX_BF-105 | Peep door broken BF-105 |
| 30 Aug 2026 | Medium | PX_BF-105 | Painting BF-105 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 21 Jul 2026 | 32 | 201000005856 | Corrective |
| 07 May 2026 | 4 | 201000033831 | Corrective |
| 03 May 2026 | 4 | 201000029703 | Corrective |
| 27 Mar 2026 | 8 | 201000038528 | Corrective |
| 20 Mar 2026 | 24 | 201000005983 | Corrective |
| 05 Feb 2026 | 12 | 204000036606 | Preventive |
| 21 Jan 2026 | 16 | 201000035361 | Corrective |
| 08 Jan 2026 | 4 | 201000013162 | Corrective |
| 02 Jan 2026 | 8 | 201000012050 | Corrective |
| 02 Jan 2026 | 96 | 201000030385 | Corrective |
| 22 Dec 2025 | 12 | 201000022442 | Corrective |
| 12 Dec 2025 | 24 | 203000018502 | Turnaround |
| 06 Dec 2025 | 12 | 201000033371 | Corrective |
| 26 Nov 2025 | 12 | 203000012255 | Turnaround |
| 27 Oct 2025 | 8 | 201000038647 | Corrective |