STUDBOLT,3/4INX65MM,B8M/8M
Material 4100024593 · STUDBOLT · Plant 1000
AReorderNormalSlow-moving
- Material
- 4100024593
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (4 of 5 FuncLocs A/B)
- Supplier
- GEMILANG MANDIRI INTERNASIONAL PT
- Lead time
- 34 d · P80 53 d
- Unit price
- Rp 15,631
Recommendation
- 1.Forecast 213 EA/year: 213 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~34 days; expected demand during lead time 20.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 118, order up to 332.
- 4.On hand 78 + on order 0 is at or below the reorder point: order 254 now.
- 5.Installed on 5 FuncLoc(s), 4 of them criticality A/B.
- 6.ML early warning: 51% probability of demand in the next 90 days.
Proposed purchase requisition
254 EA
Rp 4.0M · order by 01 Oct 2026
Expected arrival ≈ 34 days
ML early warningSingle source
On hand / on order
78 / 0
no open PO
Today Min / Max
13 / 36
static parameters in BoM
Rec. Min (reorder point)
118
safety stock 99
Rec. Max
332
order qty 214
Service level
99.9%
stockout risk now 3%
Unit price
Rp 15,631
PO history
ML early warning: 51% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 259 days ago, 17 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 5 functional locations
4 with criticality A/B · 80 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-112 CRACKING FURNACE BF-112 | A | 16 | 73 | 27.01 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 20 | 23 | 9.01 |
| PY_VD-953B METHANOL DRUM | A | 8 | 1 | 0.51 |
| PX_PP-311C REFLUX PUMP | B | 24 | 0 | 0.19 |
| PX_LCV-1992B LEVEL CONTROL VALVE | C | 12 | 0 | 0.12 |
Lead time and procurement
Lead time 34 ± 15 days (PO history, 4 PO lines) · on-time 37%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 09 Aug 2026 | PR06 Regular replenishment | 56 | Rp 14,851 | 07 Sept 2026 | 29 d |
| 24 Jul 2026 | PR06 Regular replenishment | 29 | Rp 15,817 | 23 Aug 2026 | 30 d |
| 07 Apr 2026 | PR03 Regular replenishment | 51 | Rp 15,579 | 06 Jun 2026 | 60 d |
| 04 Sept 2025 | PR06 Regular replenishment | 45 | Rp 15,683 | 22 Oct 2025 | 48 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 17 Sept 2026 | Medium | PX_BF-112 | Cleaning burner BF-112 |
| 08 Sept 2026 | Medium | PX_BF-107 | Replace lamp as per PM finding |
| 04 Sept 2026 | High | PX_BF-112 | Install scaffolding at BF-112 |
| 01 Sept 2026 | Medium | PX_BF-112 | Replace burner tip BF-112 |
| 01 Sept 2026 | Medium | PX_BF-112 | Replace burner tip BF-112 |
| 31 Aug 2026 | Medium | PX_BF-112 | Install cover plate for MCP cracking |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 15 Jan 2026 | 48 | 201000025741 | Corrective |
| 20 Dec 2025 | 8 | 201000028627 | Corrective |
| 21 Oct 2025 | 32 | 201000027084 | Corrective |