STUDBOLT,5/8INX105MM,B16/4
Material 4100024639 · STUDBOLT · Plant 1000
ASafety-criticalMonitorHealthy
- Material
- 4100024639
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (10 of 16 FuncLocs A/B, 2 safety/shutdown valve)
- Supplier
- RAJAWALI INSTRUMEN INTERNASIONAL PT
- Lead time
- 31 d · P80 37 d
- Unit price
- Rp 84,657
Recommendation
- 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 115 EA/year: 98 unplanned (recency-weighted compound poisson (own history)) + 17 from the maintenance plan.
- 3.Lead time ~31 days; expected demand during lead time 8.3.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 56, order up to 172.
- 5.Installed on 16 FuncLoc(s), 10 of them criticality A/B.
- 6.ML early warning: 93% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningLast turnaround used 96Single sourceAbnormal consumption
On hand / on order
96 / 0
no open PO
Today Min / Max
46 / 112
static parameters in BoM
Rec. Min (reorder point)
56
safety stock 48
Rec. Max
172
order qty 116
Service level
99.9%
stockout risk now 0%
Unit price
Rp 84,657
PO history
ML early warning: 93% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 160 days ago, 6 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 6 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (108 units) excluded from the baseline.
Demand pattern Lumpy · 10 issue days · 3 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 16 functional locations
10 with criticality A/B · 252 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 20 | 7 | 2.81 |
| PX_HE-126D DILUTION STEAM PREHEATER | A | 8 | 5 | 1.08 |
| PX_CL-859 FLUSHING OIL SCRUBBER | A | 24 | 2 | 0.81 |
| PX_HE-149A HYDROGEN COOLER | A | 4 | 2 | 0.65 |
| PX_TCV-264 PP-205B TEMP CONTROL | A | 24 | 0 | 0.12 |
| PX_CL-1871 CHARGE GAS SCRUBBER | B | 4 | 6 | 2.09 |
| PX_HE-632B RECYCLE ETHANE TLE | B | 24 | 2 | 0.65 |
| PX_HE-224C GASOLINE REBOILER | B | 24 | 1 | 0.22 |
| PX_LCV-413 HE-1635C LEVEL CONTROL | B | 16 | 0 | 0.12 |
| PX_PP-615A PROPYLENE PUMP | B | 24 | 0 | 0.19 |
| PX_12-LS-16976-A22A PIPE-12 FROM PP-1022 TO VD-1192 | C | 16 | 0 | 0.01 |
| PX_PRV-1934 SAFETY VALVE VD-1338 | C | 4 | 0 | 0.04 |
Lead time and procurement
Lead time 31 ± 21 days (PO history, 10 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 11 Aug 2026 | PR05 Project / turnaround | 105 | Rp 80,209 | 02 Sept 2026 | 22 d |
| 06 Aug 2026 | PR06 Regular replenishment | 183 | Rp 79,908 | 24 Aug 2026 | 18 d |
| 21 May 2026 | PR03 Regular replenishment | 122 | Rp 85,946 | 19 Jun 2026 | 29 d |
| 15 May 2026 | PR03 Regular replenishment | 186 | Rp 85,218 | 29 May 2026 | 14 d |
| 17 Apr 2026 | PR01 Import / long-lead | 58 | Rp 81,615 | 06 Jul 2026 | 80 d |
| 14 Apr 2026 | PR03 Regular replenishment | 163 | Rp 84,708 | 11 May 2026 | 27 d |
| 02 Aug 2025 | PR06 Regular replenishment | 154 | Rp 84,606 | 19 Aug 2025 | 17 d |
| 19 Jul 2025 | PR03 Regular replenishment | 140 | Rp 86,493 | 17 Aug 2025 | 29 d |
| 18 Jun 2025 | PR06 Regular replenishment | 150 | Rp 83,342 | 27 Aug 2025 | 70 d |
| 08 Jun 2025 | PR06 Regular replenishment | 157 | Rp 86,604 | 06 Jul 2025 | 28 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Jan 2027 | PX_PP-615A | Pump overhaul | 17.2 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 05 Sept 2026 | Medium | PX_PRV-1103B | Recertification PRV-1103B |
| 01 Sept 2026 | Low | PX_KT-447 | Replace lamp as per PM finding |
| 29 Aug 2026 | Low | PX_HE-126D | Replace lamp as per PM finding |
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 15 Jul 2026 | Medium | PX_KT-624A | [MSI-B-26-RXR-331/M] Replace line |
| 08 Jul 2026 | Medium | PX_KT-447 | Replace lamp as per PM finding |
| 06 Jul 2026 | Medium | PX_HE-126D | Install scaffolding at HE-126D |
| 12 Jun 2026 | Medium | PX_CL-1871 | Leak from packing |
| 11 Jun 2026 | Medium | PX_CL-1871 | Replace lamp as per PM finding |
| 13 May 2026 | Medium | PX_CL-1871 | Install scaffolding at CL-1871 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 24 Apr 2026 | 4 | 201000002099 | Corrective |
| 30 Jan 2026 | 8 | 201000013677 | Corrective |
| 18 Jan 2026 | 4 | 201000005422 | Corrective |
| 17 Nov 2025 | 96 | 201000004355 | Corrective |
| 06 Nov 2025 | 96 | 203000039255 | Turnaround |
| 04 Nov 2025 | 96 | 201000028795 | Corrective |
| 23 Sept 2025 | 8 | 201000009723 | Corrective |
| 19 Sept 2025 | 96 | 201000011776 | Corrective |
| 16 Sept 2025 | 12 | 201000009640 | Corrective |
| 25 Aug 2025 | 12 | 203000020904 | Turnaround |
| 24 Aug 2025 | 8 | 201000036234 | Corrective |
| 26 May 2025 | 16 | 201000007863 | Corrective |