STUDBOLT,3/4INX55MM,B8M/8M

Material 4100024754 · STUDBOLT · Plant 1000

ASafety-criticalMonitorTAM reserve
Material
4100024754
Category
STUDBOLT
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 7 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
No PO history
Lead time
23 d · P80 39 d
Unit price
Rp 37,807 (est.)

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 5.5 EA/year: 5.5 unplanned (installed-base failure prior (no history)).
  • 3.Lead time ~23 days; expected demand during lead time 0.3.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 27, order up to 54.
  • 5.Used only during the last turnaround (72 EA): keep it for the next one instead of treating it as slow-moving.
  • 6.Installed on 7 FuncLoc(s), 2 of them criticality A/B.
Safety-critical (SCE)Last turnaround used 72Price estimatedLead time estimated
On hand / on order
31 / 0
no open PO
Today Min / Max
25 / 68
static parameters in BoM
Rec. Min (reorder point)
27
safety stock 27
Rec. Max
54
order qty 27
Service level
100.0%
stockout risk now 0%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 9% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (72 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 44.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.

Installed on 7 functional locations

2 with criticality A/B · 116 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-621
PP-902B OUTLET FLOW
A2441.39
PX_PRV-426A
SAFETY VALVE KC-452
B2400.04
PX_3/4-IA-15384-A41A
PIPE-3/4 FROM PP-1279 TO KC-235D
C2000.01
PX_FCV-825
GASOLINE FLOW CONTROL
C400.11
PY_PCV-1975
PRESSURE CONTROL VALVE
C800.08
PX_KT-202
TURBINE FOR KC-202
S2042.81
PX_KC-511C
FUEL OIL FAN
S1610.57

Lead time and procurement

Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
28 Jun 2026MediumPX_FCV-621Install scaffolding at FCV-621
22 Jan 2026MediumPX_FCV-621Leak from packing
09 Jan 2026MediumPX_KT-202KT-202 governor valve hunting
24 Sept 2025LowPX_FCV-621Replace lamp as per PM finding
17 Sept 2025MediumPX_KT-202Replace lamp as per PM finding
24 Jul 2025MediumPX_KC-511CInstall scaffolding at KC-511C
18 Jul 2025HighPX_FCV-621FCV-621 stuck
06 Jul 2025LowPX_KT-202KT-202 steam leak at gland

Recent goods issues

Posting dateQtyOrderOrder type
09 Jan 202672203000006950Turnaround