STUDBOLT,3/4INX95MM,B8M/8M
Material 4100024869 · STUDBOLT · Plant 1000
ASafety-criticalReduceExcess
- Material
- 4100024869
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 5 FuncLocs A/B, 2 safety/shutdown valve)
- Supplier
- RAJAWALI INSTRUMEN INTERNASIONAL PT
- Lead time
- 25 d · P80 38 d
- Unit price
- Rp 15,455
Recommendation
- 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 115 EA/year: 103 unplanned (credibility blend: own history + installed-base prior) + 11 from the maintenance plan.
- 3.Lead time ~25 days; expected demand during lead time 7.1.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 100, order up to 215.
- 5.Stock 444 exceeds the level to keep (215) by 229.
- 6.Installed on 5 FuncLoc(s), 2 of them criticality A/B.
Safety-critical (SCE)Last turnaround used 36Single source
On hand / on order
444 / 0
no open PO
Today Min / Max
95 / 215
static parameters in BoM
Rec. Min (reorder point)
100
safety stock 93
Rec. Max
215
order qty 115
Service level
100.0%
stockout risk now 0%
Unit price
Rp 15,455
PO history
ML early warning: 26% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 79 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (324 units) excluded from the baseline.
Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 444.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 5 functional locations
2 with criticality A/B · 60 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-308B TURBINE FOR KC-308B | A | 12 | 0 | 1.10 |
| PX_PRV-624 SAFETY VALVE HE-232C | B | 4 | 2 | 0.90 |
| PX_LCV-775 HE-561A LEVEL CONTROL | C | 16 | 0 | 0.12 |
| PX_VD-436 DILUTION STEAM SURGE DRUM | C | 20 | 0 | 0.08 |
| PY_PRV-1528 SAFETY VALVE CL-1326 | S | 8 | 0 | 0.04 |
Lead time and procurement
Lead time 25 ± 17 days (PO history, 5 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 23 Apr 2026 | PR06 Regular replenishment | 112 | Rp 16,118 | 02 May 2026 | 9 d |
| 03 Feb 2026 | PR06 Regular replenishment | 83 | Rp 15,009 | 09 Mar 2026 | 34 d |
| 29 Jan 2026 | PR03 Regular replenishment | 233 | Rp 15,090 | 15 Feb 2026 | 17 d |
| 10 Dec 2025 | PR03 Regular replenishment | 125 | Rp 15,623 | 27 Dec 2025 | 17 d |
| 12 Sept 2025 | PR04 Regular (other) | 213 | Rp 15,455 | 07 Nov 2025 | 56 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Sept 2027 | PX_LCV-775 | Final Element Overhaul; Control Valve | 11.5 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 04 Apr 2026 | Emergency | PX_PRV-624 | Replace lamp as per PM finding |
| 07 Jul 2025 | Medium | PX_PRV-624 | PRV-624 passing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 14 Jul 2026 | 48 | 201000034553 | Corrective |
| 17 Dec 2025 | 8 | 201000011845 | Corrective |
| 29 Nov 2025 | 12 | 203000032713 | Turnaround |
| 17 Nov 2025 | 96 | 201000002039 | Corrective |
| 09 Nov 2025 | 24 | 203000039046 | Turnaround |
| 05 Oct 2025 | 48 | 201000016100 | Corrective |
| 16 Aug 2025 | 288 | 203000007731 | Turnaround |