STUDBOLT,1/2INX70MM,B16/4
Material 4100024877 · STUDBOLT · Plant 1000
AReorderNormalBelow reorder point
- Material
- 4100024877
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (3 of 4 FuncLocs A/B)
- Supplier
- ANUGRAH SARANA JAYA PT
- Lead time
- 20 d · P80 39 d
- Unit price
- Rp 65,189
Recommendation
- 1.Forecast 48 EA/year: 48 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~20 days; expected demand during lead time 2.7.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 42, order up to 91.
- 4.On hand 13 + on order 0 is at or below the reorder point: order 78 now.
- 5.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
78 EA
Rp 5.1M · order by 01 Oct 2026
Expected arrival ≈ 20 days
Single source
On hand / on order
13 / 0
no open PO
Today Min / Max
12 / 26
static parameters in BoM
Rec. Min (reorder point)
42
safety stock 40
Rec. Max
91
order qty 49
Service level
100.0%
stockout risk now 12%
Unit price
Rp 65,189
PO history
ML early warning: 17% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 172 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Lumpy · 5 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 496.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 4 functional locations
3 with criticality A/B · 60 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-1152 RECYCLE ETHANE FLOW CONTROL | A | 8 | 0 | 0.11 |
| PX_PP-866A METHANE PUMP | B | 24 | 4 | 1.90 |
| PX_3/4-BF-28395-B23A-HS PIPE-3/4 FROM HE-1201 TO PP-669A | B | 20 | 0 | 0.01 |
| PX_PP-1470A METHANE PUMP | C | 8 | 3 | 1.05 |
Lead time and procurement
Lead time 20 ± 15 days (PO history + category, 2 PO lines) · on-time 60%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 28 Oct 2025 | PR03 Regular replenishment | 47 | Rp 66,115 | 23 Nov 2025 | 26 d |
| 04 May 2025 | PR03 Regular replenishment | 30 | Rp 64,263 | 11 May 2025 | 7 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 28 Sept 2026 | Low | PX_PP-1470A | Replace lamp as per PM finding |
| 25 Mar 2026 | Medium | PX_PP-866A | Leak from packing |
| 04 Mar 2026 | Medium | PX_PP-1470A | Oil leak at PP-1470A bearing housing |
| 28 Nov 2025 | Medium | PX_PP-866A | PP-866A abnormal noise |
| 18 Oct 2025 | Low | PX_PP-866A | PP-866A seal leak |
| 28 Jun 2025 | Medium | PX_PP-866A | Replace lamp as per PM finding |
| 17 May 2025 | Medium | PX_PP-1470A | Install cover plate for MCP cracking |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 12 Apr 2026 | 48 | 201000037738 | Corrective |
| 28 Feb 2026 | 16 | 201000023129 | Corrective |
| 30 Nov 2025 | 12 | 209000037038 | Other maintenance |
| 14 Sept 2025 | 24 | 201000034468 | Corrective |
| 02 Jul 2025 | 4 | 201000030712 | Corrective |