STUDBOLT,1/2INX70MM,B7/2H
Material 4100024943 · STUDBOLT · Plant 1000
AReduceSlow-moving
- Material
- 4100024943
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (3 of 3 FuncLocs A/B)
- Supplier
- SAMUDRA SEJAHTERA INTERNASIONAL PT
- Lead time
- 21 d · P80 27 d
- Unit price
- Rp 23,305
Recommendation
- 1.Forecast 105 EA/year: 105 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~21 days; expected demand during lead time 6.1.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 71, order up to 176.
- 4.Stock 236 exceeds the level to keep (176) by 60.
- 5.Installed on 3 FuncLoc(s), 3 of them criticality A/B.
Last turnaround used 24Single source
On hand / on order
236 / 0
no open PO
Today Min / Max
72 / 121
static parameters in BoM
Rec. Min (reorder point)
71
safety stock 65
Rec. Max
176
order qty 105
Service level
99.9%
stockout risk now 0%
Unit price
Rp 23,305
PO history
ML early warning: 22% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 266 days ago, 6 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (24 units) excluded from the baseline.
Demand pattern Lumpy · 5 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 638.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 3 functional locations
3 with criticality A/B · 36 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-109 CRACKING FURNACE BF-109 | A | 8 | 29 | 11.58 |
| PX_HE-1817C WASH WATER TLE | A | 24 | 0 | 0.22 |
| PX_VD-981A FLUSHING OIL ACCUMULATOR | B | 4 | 0 | 0.08 |
Lead time and procurement
Lead time 21 ± 11 days (PO history, 5 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 09 May 2026 | PR04 Regular (other) | 48 | Rp 23,442 | 30 May 2026 | 21 d |
| 23 Apr 2026 | PR03 Regular replenishment | 89 | Rp 23,305 | 18 May 2026 | 25 d |
| 15 Feb 2026 | PR03 Regular replenishment | 40 | Rp 22,047 | 20 Mar 2026 | 33 d |
| 17 Jan 2026 | PR03 Regular replenishment | 94 | Rp 23,538 | 28 Jan 2026 | 11 d |
| 29 Oct 2025 | PR03 Regular replenishment | 80 | Rp 22,706 | 10 Nov 2025 | 12 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 20 Sept 2026 | Medium | PX_BF-109 | Thermograph wall BF-109 |
| 13 Sept 2026 | Medium | PX_BF-109 | Install scaffolding at BF-109 |
| 03 Sept 2026 | Low | PX_BF-109 | Install scaffolding at BF-109 |
| 02 Sept 2026 | Low | PX_BF-109 | Install cover plate for MCP cracking |
| 16 Aug 2026 | Medium | PX_BF-109 | Install cover plate BF-109 |
| 13 Jul 2026 | Medium | PX_BF-109 | Cleaning burner BF-109 |
| 09 Jul 2026 | Medium | PX_BF-109 | Thermograph wall BF-109 |
| 09 Jul 2026 | Low | PX_BF-109 | Leak from packing |
| 01 Jul 2026 | Emergency | PX_BF-109 | [MSI-B-26-YDN-280/M] Replace line |
| 23 Jun 2026 | High | PX_BF-109 | Cleaning burner BF-109 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 08 Jan 2026 | 32 | 201000012817 | Corrective |
| 07 Jan 2026 | 24 | 203000006950 | Turnaround |
| 30 Dec 2025 | 96 | 201000024415 | Corrective |
| 17 Oct 2025 | 4 | 201000030339 | Corrective |
| 29 Jul 2025 | 8 | 201000024339 | Corrective |
| 15 May 2025 | 36 | 209000000303 | Other maintenance |