STUDBOLT,3/4INX40MM,B16/4
Material 4100024948 · STUDBOLT · Plant 1000
AReorderNormalSlow-moving
- Material
- 4100024948
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 4 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 23 d · P80 39 d
- Unit price
- Rp 37,807 (est.)
Recommendation
- 1.Forecast 16 EA/year: 10 unplanned (credibility blend: own history + installed-base prior) + 5.7 from the maintenance plan.
- 2.Lead time ~23 days; expected demand during lead time 0.7.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 16, order up to 33.
- 4.On hand 1 + on order 0 is at or below the reorder point: order 32 now.
- 5.Installed on 4 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
32 EA
Rp 1.2M · order by 01 Oct 2026
Expected arrival ≈ 23 days
Price estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
16
safety stock 16
Rec. Max
33
order qty 17
Service level
100.0%
stockout risk now 8%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 266 days ago, 0 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 280.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 4 functional locations
1 with criticality A/B · 20 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1161 LEAN AMINE PUMP | A | 4 | 4 | 1.47 |
| PX_16-BF-26798-A41A-H PIPE->16 FROM VD-727 TO VD-1706 | C | 4 | 0 | 0.01 |
| PX_8-QO-9275-A22A-H PIPE-8 FROM HE-1025 TO HE-1968B | C | 4 | 0 | 0.01 |
| PX_KT-264A TURBINE FOR KC-264A | S | 8 | 4 | 2.39 |
Lead time and procurement
Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 26 Dec 2026 | PX_KT-264A | Turbine major overhaul | 5.73 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 11 Jun 2026 | Low | PX_KT-264A | Leak from packing |
| 29 May 2026 | Low | PX_PP-1161 | Replace lamp as per PM finding |
| 21 Apr 2026 | Low | PX_KT-264A | Follow up after steam upset KT-264A |
| 06 Jan 2026 | Low | PX_PP-1161 | Replace bearing PP-1161 |
| 21 Oct 2025 | Medium | PX_KT-264A | KT-264A governor valve hunting |
| 19 Oct 2025 | Medium | PX_PP-1161 | PP-1161 seal leak |
| 31 May 2025 | Medium | PX_KT-264A | Install scaffolding at KT-264A |
| 15 May 2025 | Low | PX_PP-1161 | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 08 Jan 2026 | 8 | 201000004561 | Corrective |