STUDBOLT,3/4INX35MM,B8M/8M
Material 4100024958 · STUDBOLT · Plant 1000
ASafety-criticalReorderNormalCritical insurance spare
- Material
- 4100024958
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (3 of 5 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- No PO history
- Lead time
- 23 d · P80 39 d
- Unit price
- Rp 37,807 (est.)
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 3.4 EA/year: 3.4 unplanned (installed-base failure prior (no history)).
- 3.Lead time ~23 days; expected demand during lead time 0.2.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 27, order up to 54.
- 5.On hand 1 + on order 0 is at or below the reorder point: order 53 now.
- 6.No issue in 17 months, but it protects critical equipment: keep it.
- 7.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
53 EA
Rp 2.0M · order by 01 Oct 2026
Expected arrival ≈ 23 days
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
27
safety stock 27
Rec. Max
54
order qty 27
Service level
100.0%
stockout risk now 1%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 27.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 5 functional locations
3 with criticality A/B · 76 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 8 | 7 | 2.81 |
| PX_PCV-1627 PRESSURE CONTROL VALVE | A | 16 | 0 | 0.08 |
| PX_PP-1969B FEED PUMP | B | 8 | 0 | 0.19 |
| PX_1-1/2-LS-6362-A21A PIPE-1-1/2 FROM VD-1513 TO PP-455D | C | 24 | 0 | 0.01 |
| PX_PRV-1147 SAFETY VALVE HE-1774A | C | 20 | 0 | 0.04 |
Lead time and procurement
Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 26 Mar 2026 | Medium | PX_KT-856A | KT-856A steam leak at gland |
| 20 Nov 2025 | Medium | PX_KT-856A | KT-856A governor valve hunting |
| 16 Nov 2025 | Low | PX_KT-856A | Install scaffolding at KT-856A |
| 04 Sept 2025 | Low | PX_KT-856A | Install scaffolding at KT-856A |
| 26 Aug 2025 | Low | PX_KT-856A | Replace lamp as per PM finding |
| 09 May 2025 | Medium | PX_KT-856A | PSM25/KT-856A steam leak at gland |
Recent goods issues
Never issued in the 17-month history.