STUDBOLT,1INX50MM,B16/4
Material 4100025085 · STUDBOLT · Plant 1000
AReorderNormalBelow reorder point
- Material
- 4100025085
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (6 of 7 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 23 d · P80 39 d
- Unit price
- Rp 37,807 (est.)
Recommendation
- 1.Forecast 31 EA/year: 31 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~23 days; expected demand during lead time 1.9.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 40, order up to 71.
- 4.On hand 22 + on order 0 is at or below the reorder point: order 49 now.
- 5.Installed on 7 FuncLoc(s), 6 of them criticality A/B.
Proposed purchase requisition
49 EA
Rp 1.9M · order by 01 Oct 2026
Expected arrival ≈ 23 days
Price estimatedLead time estimated
On hand / on order
22 / 0
no open PO
Today Min / Max
19 / 40
static parameters in BoM
Rec. Min (reorder point)
40
safety stock 39
Rec. Max
71
order qty 31
Service level
100.0%
stockout risk now 0%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 14% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 10 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 330.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 7 functional locations
6 with criticality A/B · 108 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1166B BFW PUMP | A | 24 | 2 | 0.62 |
| PX_HE-1921D QUENCH OIL REBOILER | A | 12 | 1 | 0.22 |
| PX_KC-663A CONDENSATE FAN | A | 20 | 1 | 0.57 |
| PX_HE-193B FUEL OIL PREHEATER | B | 4 | 3 | 0.65 |
| PX_PCV-1103 PRESSURE CONTROL VALVE | B | 20 | 3 | 0.51 |
| PX_HE-935A LUBE OIL CONDENSER | B | 16 | 0 | 0.22 |
| PX_ROF-735 RESTRICTION ORIFICE | C | 12 | 0 | 0.00 |
Lead time and procurement
Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 06 Sept 2026 | High | PX_HE-193B | Install scaffolding at HE-193B |
| 26 Jun 2026 | Medium | PX_PCV-1103 | PCV-1103; IA leak from regulator |
| 16 Jun 2026 | Low | PX_HE-193B | Leak from packing |
| 29 Sept 2025 | Medium | PX_PCV-1103 | Install scaffolding at PCV-1103 |
| 23 Sept 2025 | Low | PX_PP-1166B | PP-1166B seal leak |
| 14 May 2025 | Low | PX_KC-663A | Leak from packing |
| 11 May 2025 | Low | PX_HE-193B | Install scaffolding at HE-193B |
| 09 May 2025 | Medium | PX_PCV-1103 | [MSI-B-25-XXZ-362/M] Replace line |
| 05 May 2025 | Low | PX_HE-1921D | Leak from packing |
| 03 May 2025 | Medium | PX_PP-1166B | [MSI-B-25-MAP-379] Permanent repair |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 21 Sept 2026 | 8 | 201000019252 | Corrective |
| 02 Aug 2025 | 32 | 201000008449 | Corrective |