STUDBOLT,1INX100MM,B8M/8M
Material 4100025139 · STUDBOLT · Plant 1000
AMonitorCritical insurance spare
- Material
- 4100025139
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (4 of 5 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 23 d · P80 39 d
- Unit price
- Rp 37,807 (est.)
Recommendation
- 1.Forecast 4.7 EA/year: 4.7 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~23 days; expected demand during lead time 0.3.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 27, order up to 54.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.No issue in 17 months, but it protects critical equipment: keep it.
- 6.Installed on 5 FuncLoc(s), 4 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
3 / 0
no open PO
Today Min / Max
2 / 4
static parameters in BoM
Rec. Min (reorder point)
27
safety stock 27
Rec. Max
54
order qty 27
Service level
100.0%
stockout risk now 1%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 38.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 5 functional locations
4 with criticality A/B · 60 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-222B LEAN AMINE COMPRESSOR | A | 12 | 5 | 1.85 |
| PX_HE-1950 SLOP OIL EXCHANGER | A | 4 | 0 | 0.22 |
| PX_VD-1637 ETHYLENE KO DRUM | A | 20 | 0 | 0.08 |
| PX_HE-1164D QUENCH WATER CONDENSER | B | 4 | 2 | 1.08 |
| PX_KT-875 TURBINE FOR KC-875 | S | 20 | 0 | 1.10 |
Lead time and procurement
Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 04 Jul 2026 | Medium | PX_HE-1164D | Leak from packing |
| 02 Jul 2026 | High | PX_KC-222B | Replace lamp as per PM finding |
| 05 Feb 2026 | Medium | PX_KC-222B | Install scaffolding at KC-222B |
| 01 Jan 2026 | Low | PX_KC-222B | KC-222B high vibration |
| 16 Nov 2025 | Medium | PX_KC-222B | KC-222B lube oil filter DP high |
| 18 Jun 2025 | Medium | PX_HE-1164D | Leak from packing |
| 17 May 2025 | Low | PX_KC-222B | Install scaffolding at KC-222B |
Recent goods issues
Never issued in the 17-month history.