STUDBOLT,1/2INX110MM,B8M/8M

Material 4100025156 · STUDBOLT · Plant 1000

AMonitorCritical insurance spare
Material
4100025156
Category
STUDBOLT
Base unit
EA
MRP type
Stock Item
Criticality
A (3 of 4 FuncLocs A/B)
Supplier
MEGA TEKNOLOGI SENTOSA PT
Lead time
23 d · P80 39 d
Unit price
Rp 35,820

Recommendation

  • 1.Forecast 14 EA/year: 14 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~23 days; expected demand during lead time 0.9.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 27, order up to 54.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.No issue in 17 months, but it protects critical equipment: keep it.
  • 6.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
Insurance spare candidateSingle source
On hand / on order
4 / 0
no open PO
Today Min / Max
3 / 5
static parameters in BoM
Rec. Min (reorder point)
27
safety stock 27
Rec. Max
54
order qty 27
Service level
99.9%
stockout risk now 3%
Unit price
Rp 35,820
PO history
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 7 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 113.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.

Installed on 4 functional locations

3 with criticality A/B · 64 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-111
CRACKING FURNACE BF-111
A20239.01
PX_PP-790A
CHARGE GAS PUMP
A1672.76
PY_VD-262
BOTTOM ACCUMULATOR
B2000.08
PX_KT-778A
TURBINE FOR KC-778A
S801.10

Lead time and procurement

Lead time 23 ± 15 days (PO history + category, 1 PO lines) · on-time 37%

PR dateTypeQtyUnit priceDeliveryLead time
29 Jun 2026PR03
Regular replenishment
1Rp 35,82020 Jul 202621 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
23 Sept 2026MediumPX_PP-790APP-790A abnormal noise
22 Sept 2026MediumPX_BF-111Install cover plate BF-111
10 Sept 2026MediumPX_BF-111Peep door broken BF-111
03 Aug 2026MediumPX_BF-111Thermograph wall BF-111
27 Jul 2026MediumPX_PP-790AOil leak at PP-790A bearing housing
23 Jul 2026HighPX_PP-790APP-790A seal leak
11 Jul 2026MediumPX_BF-111Thermograph wall BF-111
27 Jun 2026MediumPX_BF-111Leak from packing
08 May 2026MediumPX_BF-111Repair refractory crack BF-111
20 Apr 2026EmergencyPX_BF-111Cleaning burner BF-111

Recent goods issues

Never issued in the 17-month history.