STUDBOLT,7/8INX45MM,B7/2H

Material 4100025162 · STUDBOLT · Plant 1000

AReorderNormalSlow-moving
Material
4100025162
Category
STUDBOLT
Base unit
EA
MRP type
Stock Item
Criticality
A (3 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
23 d · P80 39 d
Unit price
Rp 37,807 (est.)

Recommendation

  • 1.Forecast 96 EA/year: 96 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~23 days; expected demand during lead time 6.0.
  • 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 96, order up to 192.
  • 4.On hand 18 + on order 0 is at or below the reorder point: order 174 now.
  • 5.Installed on 3 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
174 EA
Rp 6.6M · order by 01 Oct 2026
Expected arrival ≈ 23 days
Price estimatedLead time estimated
On hand / on order
18 / 0
no open PO
Today Min / Max
10 / 23
static parameters in BoM
Rec. Min (reorder point)
96
safety stock 90
Rec. Max
192
order qty 96
Service level
99.8%
stockout risk now 6%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 356 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 214.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.

Installed on 3 functional locations

3 with criticality A/B · 16 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_VD-694A
C3 RECYCLE ACCUMULATOR
A430.93
PX_KC-588
CAUSTIC FAN
A421.00
PX_HE-695A
METHANOL TLE
B821.08

Lead time and procurement

Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
19 Jun 2026LowPX_VD-694ALeak from packing
22 Feb 2026MediumPX_KC-588KC-588 lube oil filter DP high
14 Nov 2025MediumPX_HE-695A[MSI-B-25-MUZ-221] Permanent repair
01 Oct 2025MediumPX_VD-694AInspect VD-694A
24 Jun 2025LowPX_HE-695AHE-695A tube leak
24 May 2025MediumPX_KC-588Repair insulation KC-588
09 May 2025MediumPX_VD-694APSM25/Replace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
10 Oct 202596201000006082Corrective