STUDBOLT,3/4INX100MM,B16/4
Material 4100025189 · STUDBOLT · Plant 1000
AReorderCriticalStockout
- Material
- 4100025189
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (6 of 9 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 23 d · P80 39 d
- Unit price
- Rp 37,807 (est.)
Recommendation
- 1.Forecast 96 EA/year: 96 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~23 days; expected demand during lead time 6.0.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 81, order up to 177.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 177 now.
- 5.Installed on 9 FuncLoc(s), 6 of them criticality A/B.
Proposed purchase requisition
177 EA
Rp 6.7M · order by 01 Oct 2026
Expected arrival ≈ 23 days
Last turnaround used 48Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
11 / 16
static parameters in BoM
Rec. Min (reorder point)
81
safety stock 75
Rec. Max
177
order qty 96
Service level
100.0%
stockout risk now 20%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 27% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 48 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (48 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 770.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 9 functional locations
6 with criticality A/B · 144 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 24 | 114 | 42.86 |
| PX_BF-106 CRACKING FURNACE BF-106 | A | 16 | 82 | 30.86 |
| PX_BF-109 CRACKING FURNACE BF-109 | A | 20 | 29 | 11.58 |
| PX_KC-778A CONDENSATE COMPRESSOR | A | 8 | 3 | 1.43 |
| PX_FCV-1863 BY PASS LINE | A | 4 | 0 | 0.11 |
| PX_KC-178A QUENCH OIL FAN | A | 24 | 0 | 0.57 |
| PX_LCV-603 HE-1524B LEVEL CONTROL | C | 8 | 0 | 0.12 |
| PX_LCV-622 LEVEL CONTROL VALVE | C | 24 | 0 | 0.12 |
| PX_VD-1704 CAUSTIC ACCUMULATOR | C | 16 | 0 | 0.08 |
Lead time and procurement
Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 20 Sept 2026 | Medium | PX_BF-105 | Replace lamp as per PM finding |
| 20 Sept 2026 | Medium | PX_BF-105 | Install scaffolding at BF-105 |
| 20 Sept 2026 | Medium | PX_BF-109 | Thermograph wall BF-109 |
| 19 Sept 2026 | Medium | PX_BF-106 | Cleaning burner BF-106 |
| 15 Sept 2026 | Medium | PX_BF-106 | Install cover plate BF-106 |
| 14 Sept 2026 | Low | PX_BF-105 | Install cover plate BF-105 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Nov 2025 | 48 | 203000020446 | Turnaround |