STUDBOLT,7/8INX105MM,B7/2H
Material 4100025227 · STUDBOLT · Plant 1000
ASafety-criticalMonitorCritical insurance spare
- Material
- 4100025227
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (3 of 5 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- No PO history
- Lead time
- 23 d · P80 39 d
- Unit price
- Rp 37,807 (est.)
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 2.5 EA/year: 2.5 unplanned (installed-base failure prior (no history)).
- 3.Lead time ~23 days; expected demand during lead time 0.2.
- 4.A 99.4% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 27.
- 5.No issue in 17 months, but it protects critical equipment: keep it.
- 6.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
9 / 0
no open PO
Today Min / Max
2 / 6
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
27
order qty 27
Service level
99.4%
stockout risk now 1%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 20.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 5 functional locations
3 with criticality A/B · 92 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-460B TURBINE FOR KC-460B | A | 24 | 2 | 1.96 |
| PX_HE-895B DEMIN WATER EXCHANGER | A | 24 | 0 | 0.22 |
| PX_VD-378 WASH WATER DRUM | A | 24 | 0 | 0.08 |
| PX_1-CW-12583-A21A-HS PIPE-1 FROM VD-575 TO HE-1934D | C | 12 | 0 | 0.01 |
| PX_PRV-182B SAFETY VALVE PP-700 | S | 8 | 0 | 0.04 |
Lead time and procurement
Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 12 Dec 2025 | Low | PX_KT-460B | KT-460B governor valve hunting |
| 27 Jul 2025 | Medium | PX_KT-460B | Follow up after steam upset KT-460B |
Recent goods issues
Never issued in the 17-month history.