Material 4100025316 · STUDBOLT · Plant 1000

ASafety-criticalReduceNon-moving
Material
4100025316
Category
STUDBOLT
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 7 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
No PO history
Lead time
23 d · P80 39 d
Unit price
Rp 37,807 (est.)

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 4.6 EA/year: 4.6 unplanned (installed-base failure prior (no history)).
  • 3.Lead time ~23 days; expected demand during lead time 0.3.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 27, order up to 54.
  • 5.Stock 591 exceeds the level to keep (54) by 537.
  • 6.Installed on 7 FuncLoc(s), 1 of them criticality A/B.
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
591 / 0
no open PO
Today Min / Max
10 / 19
static parameters in BoM
Rec. Min (reorder point)
27
safety stock 27
Rec. Max
54
order qty 27
Service level
100.0%
stockout risk now 0%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 37.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.

Installed on 7 functional locations

1 with criticality A/B · 72 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-419A
TURBINE FOR KC-419A
A862.81
PX_PCV-139
BY PASS DUCT
C1620.94
PX_PCV-837
BY PASS DUCT
C410.08
PX_1-LS-26233-A11A
PIPE-1 FROM VD-1230 TO PP-500
C400.01
PX_HE-163A
METHANOL EXCHANGER
C1200.22
PX_FCV-1905D
HE-163D OUTLET FLOW
S400.11
PX_PRV-1875A
SAFETY VALVE VD-1069
S2400.04

Lead time and procurement

Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
22 Apr 2026MediumPX_PCV-139Overhaul PCV-139
03 Apr 2026MediumPX_KT-419AKT-419A steam leak at gland
17 Mar 2026MediumPX_KT-419AInstall cover plate for MCP cracking
20 Nov 2025MediumPX_KT-419ALeak from packing
10 Nov 2025MediumPX_KT-419APainting KT-419A
03 Sept 2025MediumPX_KT-419AFollow up after steam upset KT-419A
17 Jun 2025MediumPX_PCV-139[MSI-B-25-ZRC-367/M] Replace line
16 May 2025LowPX_PCV-837PCV-837; IA leak from regulator
15 May 2025LowPX_KT-419APSM25/Leak from packing

Recent goods issues

Never issued in the 17-month history.