STUDBOLT,5/8INX80MM,B7/2H
Material 4100025366 · STUDBOLT · Plant 1000
AReorderCriticalStockout
- Material
- 4100025366
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 2 FuncLocs A/B)
- Supplier
- ANUGRAH PERKASA MAKMUR PT
- Lead time
- 17 d · P80 12 d
- Unit price
- Rp 59,593
Recommendation
- 1.Forecast 75 EA/year: 75 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~17 days; expected demand during lead time 3.5.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 152, order up to 304.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 304 now.
- 5.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
304 EA
Rp 18.1M · order by 01 Oct 2026
Expected arrival ≈ 17 days
Single source
On hand / on order
0 / 0
no open PO
Today Min / Max
43 / 76
static parameters in BoM
Rec. Min (reorder point)
152
safety stock 149
Rec. Max
304
order qty 152
Service level
100.0%
stockout risk now 2%
Unit price
Rp 59,593
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 347 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 106.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 2 functional locations
2 with criticality A/B · 44 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-645A SLOP OIL PUMP | A | 20 | 2 | 0.62 |
| PX_PP-1225B INHIBITOR PUMP | B | 24 | 2 | 0.62 |
Lead time and procurement
Lead time 17 ± 9 days (PO history, 3 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 09 Oct 2025 | PR03 Regular replenishment | 45 | Rp 60,616 | 19 Oct 2025 | 10 d |
| 28 Aug 2025 | PR06 Regular replenishment | 51 | Rp 57,358 | 11 Sept 2025 | 14 d |
| 01 Aug 2025 | PR03 Regular replenishment | 36 | Rp 59,593 | 08 Aug 2025 | 7 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 07 Mar 2026 | Emergency | PX_PP-1225B | [MSI-B-26-WTG-155/M] Replace line |
| 17 Nov 2025 | Medium | PX_PP-645A | Replace bearing PP-645A |
| 25 May 2025 | Medium | PX_PP-1225B | PSM25/[MSI-B-25-KAT-363/M] Replace line |
| 24 May 2025 | Medium | PX_PP-645A | PP-645A seal leak |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 19 Oct 2025 | 96 | 201000017071 | Corrective |
| 19 Oct 2025 | 24 | 201000017071 | Corrective |
| 19 Oct 2025 | 32 | 201000017071 | Corrective |