STUDBOLT,1INX30MM,B16/4
Material 4100025390 · STUDBOLT · Plant 1000
AReorderNormalSlow-moving
- Material
- 4100025390
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (8 of 9 FuncLocs A/B)
- Supplier
- BINTANG PERKASA ABADI PT
- Lead time
- 30 d · P80 43 d
- Unit price
- Rp 16,552
Recommendation
- 1.Forecast 48 EA/year: 36 unplanned (credibility blend: own history + installed-base prior) + 11 from the maintenance plan.
- 2.Lead time ~30 days; expected demand during lead time 2.9.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 40, order up to 88.
- 4.On hand 6 + on order 0 is at or below the reorder point: order 82 now.
- 5.Installed on 9 FuncLoc(s), 8 of them criticality A/B.
- 6.ML early warning: 73% probability of demand in the next 90 days.
Proposed purchase requisition
82 EA
Rp 1.4M · order by 01 Oct 2026
Expected arrival ≈ 30 days
ML early warningSingle source
On hand / on order
6 / 0
no open PO
Today Min / Max
5 / 13
static parameters in BoM
Rec. Min (reorder point)
40
safety stock 38
Rec. Max
88
order qty 48
Service level
100.0%
stockout risk now 20%
Unit price
Rp 16,552
PO history
ML early warning: 73% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 259 days ago, 4 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 581.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 9 functional locations
8 with criticality A/B · 136 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_HE-1483A C4 PRODUCT COOLER | A | 24 | 11 | 3.22 |
| PX_KC-854C FEED FAN | A | 24 | 7 | 2.28 |
| PX_KT-856A TURBINE FOR KC-856A | A | 12 | 7 | 2.81 |
| PX_KC-235D DEMIN WATER FAN | A | 16 | 2 | 1.00 |
| PX_HE-1703C METHANOL PREHEATER | A | 20 | 0 | 0.22 |
| PX_LCV-1703 PP-1325 LEVEL CONTROL | A | 4 | 0 | 0.12 |
| PX_FCV-1963B BY PASS LINE | B | 20 | 0 | 0.11 |
| PX_LCV-1053C HE-1091 LEVEL CONTROL | B | 4 | 0 | 0.12 |
| PX_FCV-381 C3 RECYCLE FLOW CONTROL | C | 12 | 2 | 0.54 |
Lead time and procurement
Lead time 30 ± 13 days (PO history, 3 PO lines) · on-time 45%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 09 Jun 2026 | PR03 Regular replenishment | 10 | Rp 16,772 | 20 Jul 2026 | 41 d |
| 01 Jan 2026 | PR03 Regular replenishment | 14 | Rp 16,171 | 24 Jan 2026 | 23 d |
| 19 Jun 2025 | PR06 Regular replenishment | 14 | Rp 16,552 | 03 Aug 2025 | 45 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Nov 2026 | PX_KC-235D | Compressor major overhaul | 11.5 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 23 Sept 2026 | Medium | PX_HE-1483A | HE-1483A fouling |
| 22 Sept 2026 | Medium | PX_KC-854C | Overhaul |
| 21 Aug 2026 | Low | PX_HE-1483A | Replace lamp as per PM finding |
| 29 Jul 2026 | Medium | PX_KC-854C | Install scaffolding at KC-854C |
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 17 Jul 2026 | Low | PX_KC-854C | Painting KC-854C |
| 15 Jul 2026 | Low | PX_HE-1483A | Painting HE-1483A |
| 28 Jun 2026 | High | PX_HE-1483A | Leak from packing |
| 08 Apr 2026 | Medium | PX_HE-1483A | HE-1483A tube leak |
| 04 Apr 2026 | Medium | PX_HE-1483A | Retubing HE-1483A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 15 Jan 2026 | 8 | 201000014196 | Corrective |
| 15 Dec 2025 | 24 | 201000020854 | Corrective |
| 30 Sept 2025 | 8 | 201000015617 | Corrective |