STUDBOLT,5/8INX90MM,B7/2H
Material 4100025542 · STUDBOLT · Plant 1000
AMonitorCritical insurance spare
- Material
- 4100025542
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 4 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 23 d · P80 39 d
- Unit price
- Rp 37,807 (est.)
Recommendation
- 1.Forecast 1.8 EA/year: 1.8 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~23 days; expected demand during lead time 0.1.
- 3.A 99.6% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 27.
- 4.No issue in 17 months, but it protects critical equipment: keep it.
- 5.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
5 / 0
no open PO
Today Min / Max
3 / 5
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
27
order qty 27
Service level
99.6%
stockout risk now 0%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 14.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 4 functional locations
2 with criticality A/B · 68 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-837C HYDROGEN FLOW CONTROL | A | 16 | 0 | 0.11 |
| PX_HE-605 WASH WATER EXCHANGER | A | 20 | 0 | 0.22 |
| PX_PCV-1300 BY PASS DUCT | C | 8 | 1 | 0.08 |
| PX_CL-1165 HYDROGEN TOWER | S | 24 | 5 | 1.23 |
Lead time and procurement
Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 13 Jan 2026 | High | PX_CL-1165 | Install scaffolding at CL-1165 |
| 07 Dec 2025 | Medium | PX_CL-1165 | Replace lamp as per PM finding |
| 01 Dec 2025 | Medium | PX_CL-1165 | Install scaffolding at CL-1165 |
| 27 Sept 2025 | Medium | PX_CL-1165 | CL-1165 DP high |
| 03 Aug 2025 | Low | PX_CL-1165 | Install scaffolding at CL-1165 |
| 05 May 2025 | Low | PX_PCV-1300 | Replace lamp as per PM finding |
Recent goods issues
Never issued in the 17-month history.