Sparely
DU

STUDBOLT,5/8INX60MM,B7/2H

Material 4100025576 · STUDBOLT · Plant 1000

AMonitorCritical insurance spare
Material
4100025576
Category
STUDBOLT
Base unit
EA
MRP type
Stock Item
Criticality
A (3 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
23 d · P80 39 d
Unit price
Rp 37,807 (est.)

Recommendation

  • 1.Forecast 2.8 EA/year: 2.8 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~23 days; expected demand during lead time 0.2.
  • 3.A 99.3% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 27.
  • 4.No issue in 17 months, but it protects critical equipment: keep it.
  • 5.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
5 / 0
no open PO
Today Min / Max
2 / 6
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
27
order qty 27
Service level
99.3%
stockout risk now 1%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 22.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.

Installed on 4 functional locations

3 with criticality A/B · 60 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1735
SPENT CAUSTIC PUMP
A1241.47
PX_CL-1319
LUBE OIL SCRUBBER
A2010.38
PX_PCV-1010D
PRESSURE CONTROL VALVE
B800.08
PX_HE-1547C
DEMIN WATER PREHEATER
C2030.65

Lead time and procurement

Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
06 May 2026MediumPX_HE-1547C[MSI-B-26-ZAH-285] Permanent repair
08 Jan 2026MediumPX_PP-1735Painting PP-1735
11 Nov 2025MediumPX_PP-1735Oil leak at PP-1735 bearing housing
08 Nov 2025MediumPX_HE-1547CInstall scaffolding at HE-1547C
01 Nov 2025MediumPX_PP-1735Replace bearing PP-1735
15 Jun 2025MediumPX_PP-1735Oil leak at PP-1735 bearing housing
25 May 2025LowPX_CL-1319Install scaffolding at CL-1319
22 May 2025MediumPX_HE-1547CHE-1547C tube leak

Recent goods issues

Never issued in the 17-month history.