STUDBOLT,3/4INX95MM,B16/4
Material 4100025977 · STUDBOLT · Plant 1000
AMonitorInsurance gap
- Material
- 4100025977
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (3 of 4 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 23 d · P80 39 d
- Unit price
- Rp 37,807 (est.)
Recommendation
- 1.Forecast 4.9 EA/year: 4.9 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~23 days; expected demand during lead time 0.3.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 27, order up to 54.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
27
safety stock 27
Rec. Max
54
order qty 27
Service level
100.0%
stockout risk now 1%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 39.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 4 functional locations
3 with criticality A/B · 64 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 20 | 7 | 2.81 |
| PX_KC-801 DEMIN WATER FAN | A | 12 | 2 | 1.43 |
| PX_ROF-701D RESTRICTION ORIFICE | B | 16 | 1 | 0.00 |
| PX_HE-1392 PROPYLENE TLE | S | 16 | 0 | 0.22 |
Lead time and procurement
Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 12 Apr 2026 | Emergency | PX_KC-801 | KC-801 high vibration |
| 26 Mar 2026 | Medium | PX_KT-856A | KT-856A steam leak at gland |
| 20 Nov 2025 | Medium | PX_KT-856A | KT-856A governor valve hunting |
| 16 Nov 2025 | Low | PX_KT-856A | Install scaffolding at KT-856A |
| 04 Sept 2025 | Low | PX_KT-856A | Install scaffolding at KT-856A |
| 26 Aug 2025 | Low | PX_KT-856A | Replace lamp as per PM finding |
| 12 Jul 2025 | Low | PX_KC-801 | KC-801 bearing temp high |
| 18 May 2025 | Low | PX_ROF-701D | Install scaffolding at ROF-701D |
| 09 May 2025 | Medium | PX_KT-856A | PSM25/KT-856A steam leak at gland |
Recent goods issues
Never issued in the 17-month history.