STUDBOLT,1INX35MM,B7/2H
Material 4100026089 · STUDBOLT · Plant 1000
AReorderCriticalSlow-moving
- Material
- 4100026089
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 3 FuncLocs A/B)
- Supplier
- CAHAYA PERKASA ABADI PT
- Lead time
- 25 d · P80 39 d
- Unit price
- Rp 73,781
Recommendation
- 1.Forecast 71 EA/year: 71 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~25 days; expected demand during lead time 4.9.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 32, order up to 104.
- 4.On hand 3 + on order 0 is at or below the reorder point: order 101 now.
- 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
101 EA
Rp 7.5M · order by 01 Oct 2026
Expected arrival ≈ 25 days
Single source
On hand / on order
3 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
32
safety stock 28
Rec. Max
104
order qty 72
Service level
100.0%
stockout risk now 46%
Unit price
Rp 73,781
PO history
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 427 days ago, 14 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 3 functional locations
2 with criticality A/B · 40 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-112 CRACKING FURNACE BF-112 | A | 8 | 73 | 27.01 |
| PX_VD-1232 FUEL OIL SURGE DRUM | A | 20 | 1 | 0.08 |
| PX_KT-383A TURBINE FOR KC-383A | S | 12 | 7 | 3.67 |
Lead time and procurement
Lead time 25 ± 15 days (PO history + category, 1 PO lines) · on-time 42%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 01 Apr 2026 | PR03 Regular replenishment | 3 | Rp 73,781 | 03 May 2026 | 32 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 17 Sept 2026 | Medium | PX_BF-112 | Cleaning burner BF-112 |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 04 Sept 2026 | High | PX_BF-112 | Install scaffolding at BF-112 |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 01 Sept 2026 | Medium | PX_BF-112 | Replace burner tip BF-112 |
| 01 Sept 2026 | Medium | PX_BF-112 | Replace burner tip BF-112 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 31 Jul 2025 | 8 | 204000013783 | Preventive |