STUDBOLT,1INX35MM,B7/2H

Material 4100026089 · STUDBOLT · Plant 1000

AReorderCriticalSlow-moving
Material
4100026089
Category
STUDBOLT
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 3 FuncLocs A/B)
Supplier
CAHAYA PERKASA ABADI PT
Lead time
25 d · P80 39 d
Unit price
Rp 73,781

Recommendation

  • 1.Forecast 71 EA/year: 71 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~25 days; expected demand during lead time 4.9.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 32, order up to 104.
  • 4.On hand 3 + on order 0 is at or below the reorder point: order 101 now.
  • 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
101 EA
Rp 7.5M · order by 01 Oct 2026
Expected arrival ≈ 25 days
Single source
On hand / on order
3 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
32
safety stock 28
Rec. Max
104
order qty 72
Service level
100.0%
stockout risk now 46%
Unit price
Rp 73,781
PO history
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 427 days ago, 14 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.

Installed on 3 functional locations

2 with criticality A/B · 40 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-112
CRACKING FURNACE BF-112
A87327.01
PX_VD-1232
FUEL OIL SURGE DRUM
A2010.08
PX_KT-383A
TURBINE FOR KC-383A
S1273.67

Lead time and procurement

Lead time 25 ± 15 days (PO history + category, 1 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
01 Apr 2026PR03
Regular replenishment
3Rp 73,78103 May 202632 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026MediumPX_BF-112Install cover plate BF-112
29 Sept 2026LowPX_BF-112Painting BF-112
27 Sept 2026MediumPX_BF-112Repair insulation BF-112
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
17 Sept 2026MediumPX_BF-112Cleaning burner BF-112
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
04 Sept 2026HighPX_BF-112Install scaffolding at BF-112
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
01 Sept 2026MediumPX_BF-112Replace burner tip BF-112
01 Sept 2026MediumPX_BF-112Replace burner tip BF-112

Recent goods issues

Posting dateQtyOrderOrder type
31 Jul 20258204000013783Preventive