STUDBOLT,1INX105MM,B16/4

Material 4100026313 · STUDBOLT · Plant 1000

CMaintainNo stock needed
Material
4100026313
Category
STUDBOLT
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
23 d · P80 39 d
Unit price
Rp 37,807 (est.)

Recommendation

  • 1.Forecast 0.6 EA/year: 0.6 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~23 days; expected demand during lead time 0.0.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
Convert to Non StockPrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 123,292/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~10 days.

Installed on 2 functional locations

0 with criticality A/B · 24 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-1236A
VD-1416A OUTLET FLOW
C2020.54
PX_3-CW-8563-B23A-T
PIPE-3 FROM HE-1392 TO HE-237B
C400.01

Lead time and procurement

Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
05 Sept 2026EmergencyPX_FCV-1236AFCV-1236A; IA leak from regulator
09 Jun 2025LowPX_FCV-1236APainting FCV-1236A

Recent goods issues

Never issued in the 17-month history.