Sparely
DU

STUDBOLT,5/8INX65MM,B8M/8M

Material 4100026430 · STUDBOLT · Plant 1000

AReorderNormalTAM reserve
Material
4100026430
Category
STUDBOLT
Base unit
EA
MRP type
Stock Item
Criticality
A (4 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
23 d · P80 39 d
Unit price
Rp 37,807 (est.)

Recommendation

  • 1.Forecast 48 EA/year: 48 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~23 days; expected demand during lead time 3.0.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 54, order up to 102.
  • 4.On hand 17 + on order 0 is at or below the reorder point: order 85 now.
  • 5.Used only during the last turnaround (72 EA): keep it for the next one instead of treating it as slow-moving.
  • 6.Installed on 4 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
85 EA
Rp 3.2M · order by 01 Oct 2026
Expected arrival ≈ 23 days
Last turnaround used 72Price estimatedLead time estimated
On hand / on order
17 / 0
no open PO
Today Min / Max
7 / 16
static parameters in BoM
Rec. Min (reorder point)
54
safety stock 51
Rec. Max
102
order qty 48
Service level
100.0%
stockout risk now 11%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 21 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (72 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 384.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.

Installed on 4 functional locations

4 with criticality A/B · 60 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-105
CRACKING FURNACE BF-105
A411442.86
PX_KC-155D
CAUSTIC BLOWER
A2400.57
PX_PP-1101A
REFLUX PUMP
A800.19
PX_TCV-577
TEMPERATURE CONTROL VALVE
A2400.12

Lead time and procurement

Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
29 Sept 2026HighPX_BF-105Repair refractory crack BF-105
20 Sept 2026MediumPX_BF-105Replace lamp as per PM finding
20 Sept 2026MediumPX_BF-105Install scaffolding at BF-105
14 Sept 2026LowPX_BF-105Install cover plate BF-105
13 Sept 2026MediumPX_BF-105Thermograph wall BF-105
06 Sept 2026MediumPX_BF-105Repair insulation BF-105
01 Sept 2026LowPX_BF-105Peep door broken BF-105
30 Aug 2026MediumPX_BF-105Painting BF-105
29 Aug 2026MediumPX_BF-105Leak from packing
27 Aug 2026MediumPX_BF-105Thermograph wall BF-105

Recent goods issues

Posting dateQtyOrderOrder type
20 Jan 202672203000029956Turnaround