STUDBOLT,1INX85MM,B8M/8M
Material 4100026609 · STUDBOLT · Plant 1000
ASafety-criticalReduceSlow-moving
- Material
- 4100026609
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (3 of 5 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- No PO history
- Lead time
- 23 d · P80 39 d
- Unit price
- Rp 37,807 (est.)
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 5.1 EA/year: 5.1 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~23 days; expected demand during lead time 0.3.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 14.
- 5.Stock 569 exceeds the level to keep (204) by 365; the level includes the 204 used in the last turnaround.
- 6.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
Safety-critical (SCE)Last turnaround used 204Price estimatedLead time estimated
On hand / on order
569 / 0
no open PO
Today Min / Max
10 / 28
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 8
Rec. Max
14
order qty 6
Service level
100.0%
stockout risk now 0%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 12% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 240 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (204 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 271.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 5 functional locations
3 with criticality A/B · 104 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1945B PROPYLENE PUMP | A | 20 | 4 | 1.47 |
| PX_VD-664B METHANE KO DRUM | A | 24 | 3 | 0.93 |
| PX_TCV-254 TEMPERATURE CONTROL VALVE | B | 24 | 0 | 0.12 |
| PX_KT-778A TURBINE FOR KC-778A | S | 16 | 0 | 1.10 |
| PX_PRV-1201 SAFETY VALVE HE-1502B | S | 20 | 0 | 0.04 |
Lead time and procurement
Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 15 Jul 2026 | Medium | PX_VD-664B | Leak from packing |
| 20 Jan 2026 | Low | PX_PP-1945B | PP-1945B high vibration |
| 27 Nov 2025 | Medium | PX_VD-664B | VD-664B level glass broken |
| 28 Aug 2025 | Low | PX_PP-1945B | Replace lamp as per PM finding |
| 13 Aug 2025 | Low | PX_PP-1945B | Install scaffolding at PP-1945B |
| 11 Aug 2025 | Medium | PX_PP-1945B | Leak from packing |
| 30 May 2025 | Low | PX_VD-664B | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 03 Feb 2026 | 4 | 201000032240 | Corrective |
| 22 Dec 2025 | 12 | 203000022966 | Turnaround |
| 19 Dec 2025 | 48 | 203000022966 | Turnaround |
| 19 Dec 2025 | 144 | 203000022966 | Turnaround |