STUDBOLT,3/4INX50MM,B8M/8M
Material 4100026631 · STUDBOLT · Plant 1000
AMonitorCritical insurance spare
- Material
- 4100026631
- Category
- STUDBOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- RAJAWALI SARANA SENTOSA PT
- Lead time
- 37 d · P80 39 d
- Unit price
- Rp 52,125
Recommendation
- 1.Forecast 3.1 EA/year: 3.1 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~37 days; expected demand during lead time 0.3.
- 3.A 98.9% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 27.
- 4.No issue in 17 months, but it protects critical equipment: keep it.
- 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Single source
On hand / on order
2 / 0
no open PO
Today Min / Max
2 / 3
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
27
order qty 27
Service level
98.9%
stockout risk now 1%
Unit price
Rp 52,125
PO history
ML early warning: 22% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 24.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 1 functional locations
1 with criticality A/B · 20 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-419A TURBINE FOR KC-419A | A | 20 | 6 | 2.81 |
Lead time and procurement
Lead time 37 ± 15 days (PO history + category, 1 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 16 May 2026 | PR06 Regular replenishment | 1 | Rp 52,125 | 01 Aug 2026 | 77 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 03 Apr 2026 | Medium | PX_KT-419A | KT-419A steam leak at gland |
| 17 Mar 2026 | Medium | PX_KT-419A | Install cover plate for MCP cracking |
| 20 Nov 2025 | Medium | PX_KT-419A | Leak from packing |
| 10 Nov 2025 | Medium | PX_KT-419A | Painting KT-419A |
| 03 Sept 2025 | Medium | PX_KT-419A | Follow up after steam upset KT-419A |
| 15 May 2025 | Low | PX_KT-419A | PSM25/Leak from packing |
Recent goods issues
Never issued in the 17-month history.