Sparely
DU

STUDBOLT,7/8INX45MM,B8M/8M

Material 4100027550 · STUDBOLT · Plant 1000

AReorderNormalSlow-moving
Material
4100027550
Category
STUDBOLT
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 5 FuncLocs A/B)
Supplier
No PO history
Lead time
23 d · P80 39 d
Unit price
Rp 37,807 (est.)

Recommendation

  • 1.Forecast 20 EA/year: 8.9 unplanned (installed-base failure prior (no history)) + 11 from the maintenance plan.
  • 2.Lead time ~23 days; expected demand during lead time 0.6.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 27, order up to 54.
  • 4.On hand 5 + on order 0 is at or below the reorder point: order 49 now.
  • 5.Installed on 5 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
49 EA
Rp 1.9M · order by 01 Oct 2026
Expected arrival ≈ 23 days
Price estimatedLead time estimated
On hand / on order
5 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
27
safety stock 27
Rec. Max
54
order qty 27
Service level
100.0%
stockout risk now 2%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (36 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 71.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.

Installed on 5 functional locations

2 with criticality A/B · 76 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_HE-1070
CONDENSATE REBOILER
A1600.22
PX_PP-1115
SLOP OIL PUMP
A2000.19
PX_KT-447
TURBINE FOR KC-447
S16136.24
PX_VD-1305A
FUEL OIL DRUM
S820.51
PX_KC-505D
METHANE COMPRESSOR
S1611.00

Lead time and procurement

Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
07 Jul 2027PX_KC-505DCompressor major overhaul11.5

Recent notifications on its equipment

DatePriorityFuncLocDescription
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
08 Jul 2026MediumPX_KT-447Replace lamp as per PM finding
13 May 2026LowPX_KT-447KT-447 trip test
19 Apr 2026LowPX_KT-447Follow up after steam upset KT-447
30 Mar 2026LowPX_KT-447Leak from packing
28 Mar 2026MediumPX_KT-447Follow up after steam upset KT-447
14 Mar 2026MediumPX_KT-447KT-447 steam leak at gland
31 Jan 2026MediumPX_VD-1305AVD-1305A level glass broken
14 Jan 2026MediumPX_KT-447Follow up after steam upset KT-447
21 Nov 2025MediumPX_KT-447Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
31 Jul 202536203000033054Turnaround