STUDBOLT,7/8INX80MM,B16/4

Material 4100027655 · STUDBOLT · Plant 1000

AReorderNormalSlow-moving
Material
4100027655
Category
STUDBOLT
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
23 d · P80 39 d
Unit price
Rp 37,807 (est.)

Recommendation

  • 1.Forecast 47 EA/year: 47 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~23 days; expected demand during lead time 3.0.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 54, order up to 102.
  • 4.On hand 9 + on order 0 is at or below the reorder point: order 93 now.
  • 5.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
93 EA
Rp 3.5M · order by 01 Oct 2026
Expected arrival ≈ 23 days
Price estimatedLead time estimated
On hand / on order
9 / 0
no open PO
Today Min / Max
7 / 14
static parameters in BoM
Rec. Min (reorder point)
54
safety stock 52
Rec. Max
102
order qty 48
Service level
100.0%
stockout risk now 11%
Unit price
Rp 37,807
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 25 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (12 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 380.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.

Installed on 2 functional locations

1 with criticality A/B · 32 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-102
CRACKING FURNACE BF-102
A167128.72
PX_BF-110
CRACKING FURNACE BF-110
S164114.58

Lead time and procurement

Lead time 23 ± 15 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
23 Sept 2026LowPX_BF-102Replace burner tip BF-102
21 Sept 2026MediumPX_BF-110Replace burner tip BF-110
17 Sept 2026MediumPX_BF-110Install scaffolding at BF-110
15 Sept 2026MediumPX_BF-110Decoking follow up BF-110
11 Sept 2026MediumPX_BF-110Leak from packing
07 Sept 2026LowPX_BF-102Thermograph wall BF-102
06 Sept 2026MediumPX_BF-102Decoking follow up BF-102
03 Sept 2026MediumPX_BF-102Replace lamp as per PM finding
03 Sept 2026LowPX_BF-110Hot spot at convection BF-110
03 Sept 2026MediumPX_BF-110Thermograph wall BF-110

Recent goods issues

Posting dateQtyOrderOrder type
27 Jun 202512203000034428Turnaround