PIPE,2IN,STD,SS316,SMLS,6M LG
Material 4100027845 · PIPE · Plant 1000
AReduceExcess
- Material
- 4100027845
- Category
- PIPE
- Base unit
- LG
- MRP type
- Stock Item
- Criticality
- A (7 of 12 FuncLocs A/B)
- Supplier
- CAHAYA PERKASA ABADI PT
- Lead time
- 32 d · P80 41 d
- Unit price
- Rp 1.2M
Recommendation
- 1.Forecast 79 LG/year: 79 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~32 days; expected demand during lead time 7.0.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 25, order up to 56.
- 4.Stock 101 exceeds the level to keep (56) by 45.
- 5.Installed on 12 FuncLoc(s), 7 of them criticality A/B.
- 6.ML early warning: 100% probability of demand in the next 90 days.
ML early warningLast turnaround used 12Single sourceAbnormal consumptionOpen PO
On hand / on order
101 / 68
next delivery 16 Oct 2026
Today Min / Max
72 / 179
static parameters in BoM
Rec. Min (reorder point)
25
safety stock 19
Rec. Max
56
order qty 31
Service level
99.9%
stockout risk now 0%
Unit price
Rp 1.2M
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 10 issue days in the last 180 days, last issue 42 days ago, 44 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 7 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (12 units) excluded from the baseline.
Demand pattern Smooth · 36 issue days · 3 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 6.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.
Installed on 12 functional locations
7 with criticality A/B · 38 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-106 CRACKING FURNACE BF-106 | A | 2 | 82 | 30.86 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 3 | 38 | 14.58 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 2 | 28 | 11.58 |
| PX_HE-322C LEAN AMINE EXCHANGER | A | 6 | 0 | 0.22 |
| PX_HE-530D FLUSHING OIL CONDENSER | A | 6 | 0 | 0.22 |
| PX_HE-1316C QUENCH WATER COOLER | B | 3 | 0 | 0.22 |
| PX_HE-362D SEAL OIL REBOILER | B | 6 | 0 | 0.22 |
| PX_HE-1368C DILUTION STEAM TLE | C | 3 | 4 | 1.50 |
| PX_HE-1808D BOTTOM COOLER | C | 2 | 1 | 0.22 |
| PX_3/4-CW-2396-A41A PIPE-3/4 FROM KC-899B TO VD-1953 | C | 3 | 0 | 0.01 |
| PX_3/4-QO-14541-B21A-C PIPE-3/4 FROM HE-251C TO PP-584A | C | 1 | 0 | 0.01 |
| PY_HE-1593C LEAN AMINE REBOILER | C | 1 | 0 | 0.22 |
Lead time and procurement
Lead time 32 ± 16 days (PO history, 17 PO lines) · on-time 42%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 12 Sept 2026 | PR03 Regular replenishment | 43 | Rp 1.2M | 22 Sept 2026 | 10 d |
| 10 Sept 2026 | PR03 Regular replenishment | 68 | Rp 1.2M | 16 Oct 2026 open | 36 d |
| 09 Sept 2026 | PR06 Regular replenishment | 31 | Rp 1.2M | 29 Sept 2026 | 20 d |
| 12 Jul 2026 | PR03 Regular replenishment | 48 | Rp 1.3M | 23 Aug 2026 | 42 d |
| 07 Jul 2026 | PR03 Regular replenishment | 31 | Rp 1.2M | 04 Aug 2026 | 28 d |
| 06 May 2026 | PR01 Import / long-lead | 35 | Rp 1.2M | 16 Jul 2026 | 71 d |
| 30 Apr 2026 | PR06 Regular replenishment | 27 | Rp 1.2M | 20 May 2026 | 20 d |
| 09 Mar 2026 | PR03 Regular replenishment | 29 | Rp 1.2M | 03 Apr 2026 | 25 d |
| 02 Jan 2026 | PR03 Regular replenishment | 36 | Rp 1.3M | 20 Feb 2026 | 49 d |
| 23 Nov 2025 | PR06 Regular replenishment | 50 | Rp 1.2M | 25 Dec 2025 | 32 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 20 Sept 2026 | Medium | PX_BF-103 | Leak from packing |
| 19 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 19 Sept 2026 | Medium | PX_BF-106 | Cleaning burner BF-106 |
| 16 Sept 2026 | Medium | PX_BF-104 | Hot spot at convection BF-104 |
| 15 Sept 2026 | Medium | PX_BF-103 | Replace lamp as per PM finding |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 20 Aug 2026 | 1 | 201000024327 | Corrective |
| 11 Aug 2026 | 1 | 201000002355 | Corrective |
| 08 Jul 2026 | 3 | 201000023707 | Corrective |
| 24 Jun 2026 | 8 | 201000001753 | Corrective |
| 21 Jun 2026 | 3 | 201000017456 | Corrective |
| 18 Jun 2026 | 4 | 201000018305 | Corrective |
| 29 Apr 2026 | 1 | 205000012364 | Other maintenance |
| 23 Apr 2026 | 4 | 204000001034 | Preventive |
| 21 Apr 2026 | 12 | 209000024091 | Other maintenance |
| 17 Apr 2026 | 1 | 201000006270 | Corrective |
| 17 Apr 2026 | 3 | 209000024091 | Other maintenance |
| 28 Feb 2026 | 3 | 201000035660 | Corrective |
| 23 Feb 2026 | 5 | 201000024861 | Corrective |
| 21 Feb 2026 | 3 | 201000019323 | Corrective |
| 30 Jan 2026 | 3 | 201000037127 | Corrective |