PIPE,8IN,STD,P11,SMLS,6M LG
Material 4100027986 · PIPE · Plant 1000
AReduceExcess
- Material
- 4100027986
- Category
- PIPE
- Base unit
- LG
- MRP type
- Stock Item
- Criticality
- A (1 of 6 FuncLocs A/B)
- Supplier
- SAMUDRA SEJAHTERA PERSADA PT
- Lead time
- 44 d · P80 63 d
- Unit price
- Rp 2.9M
Recommendation
- 1.Forecast 21 LG/year: 21 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~44 days; expected demand during lead time 2.5.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 11, order up to 22.
- 4.Stock 164 exceeds the level to keep (22) by 142.
- 5.Installed on 6 FuncLoc(s), 1 of them criticality A/B.
- 6.ML early warning: 90% probability of demand in the next 90 days.
ML early warningLast turnaround used 15Single sourceAbnormal consumption
On hand / on order
164 / 0
no open PO
Today Min / Max
14 / 40
static parameters in BoM
Rec. Min (reorder point)
11
safety stock 9
Rec. Max
22
order qty 11
Service level
99.8%
stockout risk now 0%
Unit price
Rp 2.9M
PO history
ML early warning: 90% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 5 issue days in the last 180 days, last issue 6 days ago, 14 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (18 units) excluded from the baseline.
Demand pattern Lumpy · 14 issue days · 3 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.
Installed on 6 functional locations
1 with criticality A/B · 33 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-109 CRACKING FURNACE BF-109 | A | 12 | 29 | 11.58 |
| PX_1-FG-18043-C11A-T PIPE-1 FROM PP-745 TO PP-225A | C | 2 | 2 | 0.87 |
| PX_3/4-QO-26054-D12A-C PIPE-3/4 FROM PP-615A TO VD-1420A | C | 1 | 0 | 0.01 |
| PX_HE-1008A C3 RECYCLE CONDENSER | C | 12 | 0 | 0.22 |
| PX_BF-108 CRACKING FURNACE BF-108 | S | 3 | 23 | 9.44 |
| PX_HE-1392 PROPYLENE TLE | S | 3 | 0 | 0.22 |
Lead time and procurement
Lead time 44 ± 28 days (PO history, 12 PO lines) · on-time 42%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 12 Aug 2026 | PR03 Regular replenishment | 13 | Rp 2.8M | 01 Sept 2026 | 20 d |
| 25 Jul 2026 | PR06 Regular replenishment | 36 | Rp 2.9M | 06 Sept 2026 | 43 d |
| 07 Apr 2026 | PR03 Regular replenishment | 23 | Rp 2.9M | 04 May 2026 | 27 d |
| 05 Dec 2025 | PR06 Regular replenishment | 23 | Rp 3.1M | 03 Feb 2026 | 60 d |
| 21 Nov 2025 | PR03 Regular replenishment | 27 | Rp 3.1M | 03 Jan 2026 | 43 d |
| 10 Nov 2025 | PR06 Regular replenishment | 22 | Rp 2.8M | 17 Dec 2025 | 37 d |
| 16 Oct 2025 | PR05 Project / turnaround | 36 | Rp 3.0M | 24 Dec 2025 | 69 d |
| 06 Sept 2025 | PR03 Regular replenishment | 36 | Rp 2.8M | 14 Oct 2025 | 38 d |
| 24 Jul 2025 | PR01 Import / long-lead | 27 | Rp 3.0M | 27 Nov 2025 | 126 d |
| 24 Jul 2025 | PR03 Regular replenishment | 11 | Rp 2.9M | 18 Aug 2025 | 25 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | High | PX_BF-108 | Leak from packing |
| 20 Sept 2026 | Medium | PX_BF-109 | Thermograph wall BF-109 |
| 13 Sept 2026 | Medium | PX_BF-109 | Install scaffolding at BF-109 |
| 10 Sept 2026 | Medium | PX_BF-108 | [MSI-B-26-JJB-193] Permanent repair |
| 07 Sept 2026 | Medium | PX_BF-108 | Leak from packing |
| 03 Sept 2026 | Low | PX_BF-109 | Install scaffolding at BF-109 |
| 02 Sept 2026 | Low | PX_BF-109 | Install cover plate for MCP cracking |
| 17 Aug 2026 | Low | PX_1-FG-18043-C11A-T | Replace pipe 1-FG-18043-C11A-T |
| 16 Aug 2026 | Medium | PX_BF-109 | Install cover plate BF-109 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 25 Sept 2026 | 9 | 209000029477 | Other maintenance |
| 08 Sept 2026 | 1 | 201000015787 | Corrective |
| 07 Jul 2026 | 3 | 201000003402 | Corrective |
| 21 Jun 2026 | 1 | 204000024639 | Preventive |
| 01 Jun 2026 | 1 | 201000010191 | Corrective |
| 08 Feb 2026 | 2 | 201000001822 | Corrective |
| 07 Jan 2026 | 5 | 201000014809 | Corrective |
| 07 Jan 2026 | 3 | 201000034848 | Corrective |
| 23 Nov 2025 | 1 | 201000010115 | Corrective |
| 21 Nov 2025 | 3 | 203000020131 | Turnaround |
| 10 Nov 2025 | 3 | 203000033996 | Turnaround |
| 04 Nov 2025 | 9 | 203000039255 | Turnaround |
| 26 Oct 2025 | 3 | 201000010024 | Corrective |
| 14 Oct 2025 | 1 | 201000033840 | Corrective |
| 27 Aug 2025 | 9 | 201000023083 | Corrective |