PIPE,6IN,SCH80,P11,SMLS,6M LG
Material 4100028020 · PIPE · Plant 1000
AMonitorExcess
- Material
- 4100028020
- Category
- PIPE
- Base unit
- LG
- MRP type
- Stock Item
- Criticality
- A (5 of 5 FuncLocs A/B)
- Supplier
- SINAR TEKNIK INTERNASIONAL PT
- Lead time
- 23 d · P80 25 d
- Unit price
- Rp 2.9M
Recommendation
- 1.Forecast 33 LG/year: 33 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~23 days; expected demand during lead time 2.1.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 12, order up to 26.
- 4.Installed on 5 FuncLoc(s), 5 of them criticality A/B.
- 5.ML early warning: 84% probability of demand in the next 90 days.
ML early warningLast turnaround used 39Single sourceAbnormal consumption
On hand / on order
35 / 0
no open PO
Today Min / Max
18 / 39
static parameters in BoM
Rec. Min (reorder point)
12
safety stock 10
Rec. Max
26
order qty 14
Service level
99.8%
stockout risk now 0%
Unit price
Rp 2.9M
PO history
ML early warning: 84% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 4 issue days in the last 180 days, last issue 18 days ago, 10 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (39 units) excluded from the baseline.
Demand pattern Lumpy · 10 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.
Installed on 5 functional locations
5 with criticality A/B · 19 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-112 CRACKING FURNACE BF-112 | A | 2 | 73 | 27.01 |
| PX_HE-1913 DILUTION STEAM TLE | A | 2 | 1 | 0.22 |
| PX_HE-949A SEAL OIL PREHEATER | A | 2 | 1 | 0.65 |
| PX_HE-1596B HYDROGEN TLE | A | 12 | 0 | 0.22 |
| PX_HE-119A ETHYLENE PREHEATER | B | 1 | 0 | 0.22 |
Lead time and procurement
Lead time 23 ± 12 days (PO history, 8 PO lines) · on-time 37%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 29 Jun 2026 | PR03 Regular replenishment | 26 | Rp 2.9M | 17 Jul 2026 | 18 d |
| 18 May 2026 | PR03 Regular replenishment | 35 | Rp 2.9M | 01 Jun 2026 | 14 d |
| 12 Apr 2026 | PR06 Regular replenishment | 16 | Rp 2.9M | 23 Apr 2026 | 11 d |
| 13 Feb 2026 | PR06 Regular replenishment | 16 | Rp 2.9M | 08 Mar 2026 | 23 d |
| 20 Nov 2025 | PR03 Regular replenishment | 34 | Rp 3.0M | 17 Dec 2025 | 27 d |
| 17 Nov 2025 | PR06 Regular replenishment | 36 | Rp 2.9M | 08 Dec 2025 | 21 d |
| 31 Oct 2025 | PR06 Regular replenishment | 17 | Rp 2.8M | 14 Nov 2025 | 14 d |
| 23 Jun 2025 | PR05 Project / turnaround | 11 | Rp 3.0M | 02 Aug 2025 | 40 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 17 Sept 2026 | Medium | PX_BF-112 | Cleaning burner BF-112 |
| 04 Sept 2026 | High | PX_BF-112 | Install scaffolding at BF-112 |
| 01 Sept 2026 | Medium | PX_BF-112 | Replace burner tip BF-112 |
| 01 Sept 2026 | Medium | PX_BF-112 | Replace burner tip BF-112 |
| 31 Aug 2026 | Medium | PX_BF-112 | Install cover plate for MCP cracking |
| 17 Aug 2026 | Medium | PX_BF-112 | Painting BF-112 |
| 15 Aug 2026 | Low | PX_BF-112 | Decoking follow up BF-112 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 13 Sept 2026 | 1 | 201000035506 | Corrective |
| 25 Jul 2026 | 6 | 201000003691 | Corrective |
| 13 Jul 2026 | 2 | 201000029732 | Corrective |
| 21 Apr 2026 | 1 | 201000007143 | Corrective |
| 15 Mar 2026 | 1 | 201000001103 | Corrective |
| 15 Mar 2026 | 2 | 201000001103 | Corrective |
| 21 Jan 2026 | 2 | 201000009101 | Corrective |
| 21 Jan 2026 | 1 | 201000009101 | Corrective |
| 22 Dec 2025 | 12 | 203000001878 | Turnaround |
| 11 Dec 2025 | 1 | 201000020533 | Corrective |
| 12 Nov 2025 | 27 | 203000023445 | Turnaround |
| 20 Aug 2025 | 4 | 201000008115 | Corrective |
| 10 Jul 2025 | 15 | 209000024650 | Other maintenance |
| 10 May 2025 | 5 | 201000012393 | Corrective |