PIPE,1/2IN,SCH40,SS316,SMLS,6M LG

Material 4100028060 · PIPE · Plant 1000

AMonitorHealthy
Material
4100028060
Category
PIPE
Base unit
LG
MRP type
Stock Item
Criticality
A (4 of 7 FuncLocs A/B)
Supplier
SURYA INSTRUMEN MAKMUR PT
Lead time
32 d · P80 48 d
Unit price
Rp 499,298

Recommendation

  • 1.Forecast 26 LG/year: 26 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~32 days; expected demand during lead time 2.3.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 13, order up to 40.
  • 4.Installed on 7 FuncLoc(s), 4 of them criticality A/B.
  • 5.ML early warning: 91% probability of demand in the next 90 days.
ML early warningLast turnaround used 6Single sourceAbnormal consumptionOpen PO
On hand / on order
6 / 15
next delivery 11 Oct 2026
Today Min / Max
4 / 9
static parameters in BoM
Rec. Min (reorder point)
13
safety stock 11
Rec. Max
40
order qty 27
Service level
99.9%
stockout risk now 0%
Unit price
Rp 499,298
PO history
ML early warning: 91% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 6 issue days in the last 180 days, last issue 2 days ago, 8 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (6 units) excluded from the baseline.

Demand pattern Intermittent · 11 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.

Installed on 7 functional locations

4 with criticality A/B · 46 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-107
CRACKING FURNACE BF-107
A3239.01
PX_HE-1747A
SEAL OIL COOLER
A1200.22
PX_HE-184B
RECYCLE ETHANE COOLER
A100.22
PX_HE-1650B
INHIBITOR REBOILER
B300.22
PX_HE-1912
QUENCH OIL EXCHANGER
C1241.08
PX_HE-1808D
BOTTOM COOLER
C310.22
PX_10-HS-13859-A41A-H
PIPE-10 FROM PP-743D TO HE-1822A
C1200.01

Lead time and procurement

Lead time 32 ± 20 days (PO history, 6 PO lines) · on-time 34%

PR dateTypeQtyUnit priceDeliveryLead time
08 Aug 2026PR06
Regular replenishment
19Rp 506,55927 Aug 202619 d
03 Aug 2026PR03
Regular replenishment
15Rp 499,56911 Oct 2026
open
69 d
28 Jun 2026PR06
Regular replenishment
9Rp 505,22413 Jul 202615 d
19 Mar 2026PR06
Regular replenishment
11Rp 490,26209 Apr 202621 d
21 Oct 2025PR04
Regular (other)
13Rp 499,02608 Dec 202548 d
16 Jul 2025PR01
Import / long-lead
14Rp 487,59010 Aug 202525 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
24 Sept 2026LowPX_BF-107Install scaffolding at BF-107
08 Sept 2026MediumPX_BF-107Replace lamp as per PM finding
15 Aug 2026MediumPX_BF-107Hot spot at convection BF-107
08 Aug 2026LowPX_BF-107Cleaning burner BF-107
02 Aug 2026MediumPX_HE-1912Replace lamp as per PM finding
21 Jul 2026MediumPX_BF-107Replace lamp as per PM finding
21 Jul 2026MediumPX_BF-107Thermograph wall BF-107
18 Jul 2026EmergencyPX_BF-107Hot spot at convection BF-107
10 Jul 2026MediumPX_BF-107Hot spot at convection BF-107
12 Apr 2026MediumPX_BF-107Decoking follow up BF-107

Recent goods issues

Posting dateQtyOrderOrder type
29 Sept 20264201000002157Corrective
02 Sept 20262201000017898Corrective
27 Aug 20261201000039395Corrective
13 May 20261201000038242Corrective
02 May 20261201000028818Corrective
14 Apr 20262201000012829Corrective
11 Mar 20265201000004282Corrective
25 Dec 202510201000030056Corrective
27 Nov 20256203000012255Turnaround
15 Nov 20252201000032883Corrective
07 Jun 20253201000039705Corrective
19 May 20255204000017830Preventive