PIPE,1/2IN,SCH40,CS,SMLS,6M LG
Material 4100028090 · PIPE · Plant 1000
ALong-leadMonitorCritical insurance spare
- Material
- 4100028090
- Category
- PIPE
- Base unit
- LG
- MRP type
- Stock Item
- Criticality
- A (3 of 5 FuncLocs A/B)
- Supplier
- SAMUDRA SEJAHTERA PERSADA PT
- Lead time
- 56 d · P80 93 d
- Unit price
- Rp 726,539
Recommendation
- 1.Forecast 1.4 LG/year: 1.4 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~56 days; expected demand during lead time 0.2.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.No issue in 17 months, but it protects critical equipment: keep it.
- 6.Long lead time: 80% of deliveries took up to 93 days and the fastest seen in its category 13 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 7.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
Insurance spare candidateLong-leadSingle source
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
6
order qty 3
Service level
99.8%
stockout risk now 7%
Unit price
Rp 726,539
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 6 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 127.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.
Installed on 5 functional locations
3 with criticality A/B · 17 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-111 CRACKING FURNACE BF-111 | A | 1 | 23 | 9.01 |
| PX_HE-388A CHARGE GAS EXCHANGER | A | 3 | 5 | 1.93 |
| PX_HE-372C HYDROGEN REBOILER | B | 6 | 0 | 0.22 |
| PX_3/4-QO-14676-B23A-T PIPE-3/4 FROM PP-785A TO PP-681B | C | 6 | 0 | 0.01 |
| PX_6-BF-27301-A41A-T PIPE-6 FROM VD-1133 TO KC-930C | C | 1 | 0 | 0.01 |
Lead time and procurement
Lead time 56 ± 19 days (PO history, 3 PO lines) · on-time 42%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 02 Sept 2025 | PR03 Regular replenishment | 1 | Rp 722,773 | 15 Dec 2025 | 104 d |
| 09 Aug 2025 | PR06 Regular replenishment | 2 | Rp 730,550 | 13 Oct 2025 | 65 d |
| 10 Jun 2025 | PR04 Regular (other) | 2 | Rp 726,539 | 26 Aug 2025 | 77 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 24 Sept 2026 | Medium | PX_HE-388A | Replace lamp as per PM finding |
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 10 Sept 2026 | Medium | PX_BF-111 | Peep door broken BF-111 |
| 05 Aug 2026 | Medium | PX_HE-388A | HE-388A fouling |
| 03 Aug 2026 | Medium | PX_BF-111 | Thermograph wall BF-111 |
| 11 Jul 2026 | Medium | PX_BF-111 | Thermograph wall BF-111 |
| 27 Jun 2026 | Medium | PX_BF-111 | Leak from packing |
| 23 Jun 2026 | Low | PX_HE-388A | Install scaffolding at HE-388A |
| 08 May 2026 | Medium | PX_BF-111 | Repair refractory crack BF-111 |
| 20 Apr 2026 | Emergency | PX_BF-111 | Cleaning burner BF-111 |
Recent goods issues
Never issued in the 17-month history.