Sparely
DU

PIPE,1IN,STD,SS316,SMLS,6M LG

Material 4100028152 · PIPE · Plant 1000

AMonitorInsurance gap
Material
4100028152
Category
PIPE
Base unit
LG
MRP type
Stock Item
Criticality
A (1 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
29 d · P80 51 d
Unit price
Rp 1.7M (est.)

Recommendation

  • 1.Forecast 4.9 LG/year: 4.9 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~29 days; expected demand during lead time 0.4.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 11.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
2 / 6
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
11
order qty 5
Service level
100.0%
stockout risk now 12%
Unit price
Rp 1.7M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 28 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 459.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.

Installed on 2 functional locations

1 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-106
CRACKING FURNACE BF-106
A18230.86
PX_BF-108
CRACKING FURNACE BF-108
S3239.44

Lead time and procurement

Lead time 29 ± 18 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
29 Sept 2026MediumPX_BF-106Decoking follow up BF-106
29 Sept 2026MediumPX_BF-106Decoking follow up BF-106
28 Sept 2026LowPX_BF-106Peep door broken BF-106
25 Sept 2026MediumPX_BF-108Repair refractory crack BF-108
24 Sept 2026HighPX_BF-108Leak from packing
19 Sept 2026MediumPX_BF-106Cleaning burner BF-106
15 Sept 2026MediumPX_BF-106Install cover plate BF-106
14 Sept 2026LowPX_BF-106Peep door broken BF-106
10 Sept 2026MediumPX_BF-106Replace burner tip BF-106
10 Sept 2026MediumPX_BF-108[MSI-B-26-JJB-193] Permanent repair

Recent goods issues

Never issued in the 17-month history.