PIPE,3/4IN,SCH40,CS,SMLS,6M LG
Material 4100028191 · PIPE · Plant 1000
AReduceSlow-moving
- Material
- 4100028191
- Category
- PIPE
- Base unit
- LG
- MRP type
- Stock Item
- Criticality
- A (4 of 5 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 29 d · P80 51 d
- Unit price
- Rp 1.7M (est.)
Recommendation
- 1.Forecast 56 LG/year: 56 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~29 days; expected demand during lead time 4.5.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 24, order up to 47.
- 4.Stock 107 exceeds the level to keep (47) by 60.
- 5.Installed on 5 FuncLoc(s), 4 of them criticality A/B.
Last turnaround used 15Price estimatedLead time estimated
On hand / on order
107 / 0
no open PO
Today Min / Max
5 / 15
static parameters in BoM
Rec. Min (reorder point)
24
safety stock 20
Rec. Max
47
order qty 23
Service level
99.9%
stockout risk now 0%
Unit price
Rp 1.7M
Category + unit estimate
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 356 days ago, 22 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (15 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.
Installed on 5 functional locations
4 with criticality A/B · 18 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-106 CRACKING FURNACE BF-106 | A | 12 | 82 | 30.86 |
| PX_HE-693B ETHYLENE EXCHANGER | A | 1 | 3 | 1.08 |
| PX_HE-721D LUBE OIL PREHEATER | A | 1 | 0 | 0.22 |
| PX_2-P-2392-A22A PIPE-2 FROM PP-752B TO PP-497A | B | 2 | 0 | 0.01 |
| PX_3/4-QO-1020-A21A PIPE-3/4 FROM HE-706A TO KC-226 | C | 2 | 0 | 0.01 |
Lead time and procurement
Lead time 29 ± 18 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 21 Sept 2026 | Medium | PX_HE-693B | Retubing HE-693B |
| 19 Sept 2026 | Medium | PX_BF-106 | Cleaning burner BF-106 |
| 15 Sept 2026 | Medium | PX_BF-106 | Install cover plate BF-106 |
| 14 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 10 Sept 2026 | Medium | PX_BF-106 | Replace burner tip BF-106 |
| 08 Sept 2026 | Low | PX_BF-106 | Leak from packing |
| 08 Sept 2026 | Medium | PX_BF-106 | Painting BF-106 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 21 Dec 2025 | 15 | 203000033370 | Turnaround |
| 10 Oct 2025 | 6 | 201000027944 | Corrective |