Sparely
DU

PIPE,3IN,SCH40,SS316,SMLS,6M LG

Material 4100028227 · PIPE · Plant 1000

AReorderCriticalSlow-moving
Material
4100028227
Category
PIPE
Base unit
LG
MRP type
Stock Item
Criticality
A (1 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
29 d · P80 51 d
Unit price
Rp 1.7M (est.)

Recommendation

  • 1.Forecast 37 LG/year: 37 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~29 days; expected demand during lead time 2.9.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 20, order up to 38.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 36 now.
  • 5.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
36 LG
Rp 61.6M · order by 01 Oct 2026
Expected arrival ≈ 29 days
Price estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
20
safety stock 18
Rec. Max
38
order qty 18
Service level
99.9%
stockout risk now 36%
Unit price
Rp 1.7M
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 328 days ago, 19 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.

Installed on 3 functional locations

1 with criticality A/B · 11 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-103
CRACKING FURNACE BF-103
A33814.58
PX_3-P-29227-A22A-HS
PIPE-3 FROM VD-826 TO VD-1706
C600.01
PX_BF-108
CRACKING FURNACE BF-108
S2239.44

Lead time and procurement

Lead time 29 ± 18 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026LowPX_BF-103Leak from packing
25 Sept 2026MediumPX_BF-108Repair refractory crack BF-108
24 Sept 2026HighPX_BF-108Leak from packing
20 Sept 2026MediumPX_BF-103Leak from packing
19 Sept 2026LowPX_BF-103Leak from packing
15 Sept 2026MediumPX_BF-103Replace lamp as per PM finding
11 Sept 2026MediumPX_BF-103Decoking follow up BF-103
10 Sept 2026MediumPX_BF-108[MSI-B-26-JJB-193] Permanent repair
07 Sept 2026MediumPX_BF-108Leak from packing
26 Aug 2026MediumPX_BF-103Replace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
07 Nov 20251201000010135Corrective
07 Nov 20252201000010135Corrective
06 Nov 20258201000010135Corrective
06 Nov 20252201000010135Corrective